Assembly instructions Screw compressor SKL 1200 C
Installation and assembly
22
6.6
Pressure flange
Requirements
The pressure flange must meet the following requirements:
sufficient mechanical solidity
temperature resistant up to 250°C
Minimum diameter DN 90
Ensurance or a sufficient distance to the drive components
in assembled state
Use the following screws to attach the pressure flange to the
compressor:
Screw
Standard
Solidity
Torque
Screw-in depth in the housing
of the compressor
M10x25
ISO 4762
8.8
35 Nm
13…16 mm
ATTENTION!
Too high torque or the use of unsuitable screws
can cause damage at the compressor!
6.7
Suction and pressure line
Requirements
The suction and pressure lines must meet the following
requirements:
corrosion-proof
temperature resistant up to 250°C
Minimum diameter:
Suction line: DN 125
Pressure line: DN 90
Installation
The following points must be observed during installation:
The lines must not exert any reaction force on the
compressor. Support the lines, if necessary.
Lay the pressure line falling away from the compressor.
Install a condensate sack with drain outlet at the lowest
point.
When using a plastic hose in connection with a remote
suction filter ensure that the areas around the clamps are
leak-proof.
In the event of initial soiling on the suction side, a strainer
must be temporarily mounted directly on the suction flange
during start-up.
(Recommended mesh width: 0.1 mm).