Cooper Lighting Sure-Lites LEM Installation Instructions Download Page 1

SURE-LITES

LEM 

page 1

Installation Instructions for the Sure-Lites LEM Emergency Light

IMPORTANT SAFEGUARDS

WHEN USING ELECTRICAL EQUIPMENT, BASIC SAFETY PRECAUTIONS SHOULD 

ALWAYS BE OBSERVED INCLUDING THE FOLLOWING

1.

 

READ AND FOLLOW ALL SAFETY INSTRUCTIONS

2.  2.  Do not use outdoors.
3. Do not use in hazardous locations, or near gas or electric heaters.
4. Do not let power supply cords touch hot surfaces.
5. Do not use this equipment for other than the intended use.
6. Installation is to be performed only by qualified personnel.
7. Install in accordance with National Electric Code and local regulatory agency requirements.
8. The use of accessory equipment not recommended by the manufacturer may cause an

unsafe condition.

9. Equipment should be mounted in locations and at heights where it will not readily be subjected to tampering by

unauthorized personnel.

10.

SAVE THESE INSTRUCTIONS

INSTALLATION

Step 1

  De-energize the circuit at the junction box (J-box) where the emergency light is to be installed. 

Step 2

  Open the emergency light by inserting a screwdriver in the two slots at the bottom of the unit, then 

tipping the cover up off of the backplate.

Step 3

  To mount to a junction box - Drill out the appropriate mounting pattern and the wire pass hole in 

the backplate to fit the J-box being used.

Step 4

  To mount to conduit – Cut out the U shaped knockout on the cover using snips, then attach the 

½” conduit hub to the backplate

Step 5

  Once the backplate is secured, the housing can be held in place during installation using the EZ 

Hang feature. (see Fig. 1)

Step 6

  Connect the incoming wires to the LEM power supply wires using the wire nuts provided. 

Connect the white wire to neutral. If using 120V, connect the black wire to the hot lead. If using 
277V, connect the orange wire to the hot lead. Cap the unused lead. Secure the emergency light 
to the wall and/or junction box using installer supplied hardware. 

Step 7

  Snap the cover onto the backplate.

Step 8

  Remove the EZ key battery disconnect. 

Step 9

  Energize AC supply. The test button should illuminate, and LED heads will illuminate briefly when 

the test button is pushed.

Step 10

  Adjust the heads as needed. The LEM heads utilize a highly directional beam, so the head is 

adjustable in 3 axes, not the usual 2. (see Fig. 2)

Step 11

  If the LEM is to be powered down for an extended period after initial installation, replace the EZ Key. This will prevent the battery from discharging 

when AC power is removed. However, it will also prevent the battery from charging when AC power is restored, so it must be removed once the 
unit is ready for regular operation.

Risk of Electric Shock

Disconnect power at fuse

or circuit breaker before

installing or servicing.

Risk of Fire/Electric 

Shock

If not qualified, consult an

electrician.

Figure 1

Figure 2

Slide snaps 
through holes 
in housing for 
temporary mount 
when wiring

Reviews: