To power the eNode
DO
you
need a 24V (AC/DC) power
cable. This can be newly
installed in any electrical cable
using a standard 220V>24V
transformer, or can be found on
site as often available in the
technical rooms.
eNode
DO
is studied to
interrupt any signal or current
on a SINGLE PHASE.
Therefore, isolate and cut the
single wire that needs to be
interrupted and controlled
remotely and connect with the
Relais-wires of the eNode.
Press the power button all the
way down.
The eNode will start to power
on.
Only after 30-40 seconds,
the LED will switch on
.
Secure the eNode to a good and
protected location using zip-ties
or strong tape.
Examples of possible use:
- signal to turn on boilers
- signal to turn on lights
- power cable to power ventilation
- power cable to power lights
etc.
Power the eNode with
a 24V power source
Connect the eNode
with the cable to
interrupt
Power on the
eNode
Fix the eNode on a
firm surface
INSTALLATION IS
NOW COMPLETE!
1
2
3
4
3
4
2
1
1
st
Issue
11/19
3
DIM
3
10
e