3 Installation Field

To properly assure a durable installation, various prereq-
uisites must be fulfilled:

 

For plain tile and similar roofings on roof battens a wa-
ter proof and diffusion resistant sarking (no vapor bar-
rier!) is required, with at least 24 mm strong counter 
battens to assure proper backside venting (Fig. 8). If 
the proper backside ventilation is not assured through 
ridge or eaves, ventilations tiles have to be installed 
horizontally above and below the collector field with a 
spacing of approx. 90 cm.

 

For classic slate roofings on wood boarding an undam-
aged water proof and diffusion resistant sarking has to 
be laid. Below and above the collector field a roof vent 
should be provided for approx. every 90 cm.

 

Keep a minimum distance of one meter between col-
lector fields and roof structures that emit moist air, such 
as chimneys, skylights, kitchen and air condition vents. 
Otherwise there is a risk that additional moisture enters 
the collectors through the ventilation openings in their 
frames.

 

At least three rows of roof tiles should be kept above 
and below the collector field.

 

The roof tile rows above the collector have to project 
for at least 150 mm over the upper flashing sheet.

Procedure: For plain tile or similar roofing use the existing 
roof battens as support construction. Affix the required 
additional battens according to the dimensions in Fig. 7.
and Fig. 8. 
For slate roofing without underlying roof battens install 
the collector fixing clips and all other components directly 
onto the base.
Ideally determine the installation field so that on one side 
there will be a distance of approx. 35 mm between collec-
tors and roofing slates. On the other side cut tiles/slates to 
size. For large roofing areas it is recommended to average 
out the collector field.

Table

 

3

 

Dimensions for Installation (mm)

No. of 
collectors

 
Collector field width

 
Installation field width A

1 collector

1215

1285

2 collectors

2435

2505

3 collectors

3655

3725

4 collectors

4875

4945

Fig. 7  Dimensions of installation field and positions of installation battens in mm. Choose batten thickness based upon existing battens. 

 

Additionally required battens are coloured grey (5 pieces); batten length ≥ A (width of installation field).

Summary of Contents for EURO L20

Page 1: ...d tiles Installation with classic slates generally is carried out in the same way Fig 1 Partial view of EURO roof integration with plain tile roofing Content 1 General Safety Notes 2 1 1 Symbols 2 1 2...

Page 2: ...p Maintenance For maintenance notes and additional information about setup and operation of the collector field please refer to the technical information Solar Thermal Systems 1 5 Notes on Proper Coll...

Page 3: ...d Make sure that no pure water re mains in collector during risk of frost 1 7 Recycling Note At the end of the long operational lifetime the valuable materials of the installation should be recycled i...

Page 4: ...anels slate plain tile 28 819 720 99 10 Silicone T profile 1 819 450 10 11 Corner wedge bottom left 2 parts 1 819 720 95 819 721 06 12 Corner wedge bottom right 2 parts 1 819 720 98 819 721 07 13 Flas...

Page 5: ...1 819 450 20 5 Cellular rubber tape 2 110 101 23 6 Collector fixing clip top 2 190 102 15 7 Silicone T profile 1 819 450 10 8 Flashing sheet bottom 1 819 720 96 9 Collector fixing clip bottom 1 819 72...

Page 6: ...s At least three rows of roof tiles should be kept above and below the collector field The roof tile rows above the collector have to project for at least 150 mm over the upper flashing sheet Procedur...

Page 7: ...Counter battens 3 Sub membrane lower delta sarking 4 Rafters 5 Vapor proof sarking 6 Backside ventilation space Fig 9 Serial connection of horizontally installation max 6 collectors Connection of more...

Page 8: ...ors with approx 8 mm spacing 2 Fig 12 Insert silicone T profile between collectors Alternately push ing and pulling eases work Then push collectors together until flush Fig 13 Screw on upper collector...

Page 9: ...ollector connection hose stainless steel 18 mm to the solar circuit for example via double socket or compression ring coupling Fig 18 Slip rubber seal over cable insert solar sensor into sensor sleeve...

Page 10: ...led through the tiles to afix them on the battens Fig 26 Position the following tiles as in Fig 22 and Fig 23 align at upper edge of following batten afix with nail Fig 27 Cover each panel properly wi...

Page 11: ...Fig 31 Interlock upper flashing sheets into one another at the crimped edges use rear ear for fixing sheets against sliding details above Fig 32 Lay upper flashing sheet in place and push sheet groov...

Page 12: ...bH www consolar de 12 Kasseler Stra e 1a 60486 Frankfurt a M 49 0 7621 42 228 501 Fig 35 Secure each flashing sheet with two central sheet metal screws Abb 36 Readily installed EURO roof integration o...