Figure 2: Prefabricated foundation - side view

Figure 3: Prefabricated foundation - top view

 

 For the use of the prefabricated foundation 

proceed as follows:

1.  For the prefabricated foundation, dig an 

excavation pit with a minimum area of 100 

x 80 cm and a minimum depth of 60 cm.

2.  Make a compacted gravel bed.
3.  Pull only one supply cable at a time 

through the empty conduits in the prefa-

bricated foundation.

4.  Bring the prefabricated foundation into 

position so that the upper edge of the 

foundation plate coincides with the top 

edge of the finished floor.

5.  Underlay the prefabricated foundation and 

level the foundation with a spirit level.                    

  3.4.2  Casting of an own foundation with foundation 

 

 plate

If you want to pour your own foundation, use 

our foundation plate. It already has the right 

size, the hole for the empty pipe is already 

there and the threaded rods are fixed in the 

right place. 

Figure 4: Foundation plate - side view

  

Figure 5: Foundation plate - top view

To cast your own foundation with foundation 

plate, proceed as follows:

1.  For the foundation, dig an excavation pit 

with a minimum area of 100 x 80 cm and a 

minimum depth of 60 cm.

2.  Make a firm gravel bed.
3.  Fix the foundation plate in the desired 

position. The short ends of the threaded 

rod stand vertically upwards. The upper 

edge of the foundation plate corresponds 

to the top edge of the finished floor. 

4.  Pull only one supply cable at a time 

through the empty conduits.

5. 

Insert the empty conduits about 5 cm 

through the holes in the foundation plate 

and fix the empty conduits.

6.  Lay the empty conduits as required.
7.  Align the foundation plate with the spirit 

level.

8.  Pour out the excavation pit so that the 

concrete is in complete contact with the 

underside of the foundation plate. The 

upper side of the foundation plate must 

not be covered with concrete.                                                                                

  3.4.3  Casting of an own foundation without 

 

  foundation plate

To cast your own foundation without founda

-

tion plate, proceed as follows: 
9.  For the foundation, dig an excavation pit 

with a minimum area of 100 x 80 cm and a 

Summary of Contents for X-pay

Page 1: ...Installation manual Compleo X pay 215041 b 02 2022...

Page 2: ...2 10...

Page 3: ...he wall 5 3 4 Mounting of the column 5 3 4 1 Use of the prefabricated foundation 5 3 4 2 Casting of an own foundation with foundation plate 6 3 4 3 Casting of an own foundation without foundation plat...

Page 4: ...it rains when installing the payment ter minal make sure to protect the payment terminal from water Do not use explosive or readily flammable substances in the vicinity of the payment terminal Before...

Page 5: ...er and a circuit breaker an overvol tage protection must always be installed in the sub distribution We recommend the Dehn Guard DG TT 5 275 as surge protection 3 3 Mounting of the payment terminal on...

Page 6: ...ide view Figure 5 Foundation plate top view To cast your own foundation with foundation plate proceed as follows 1 For the foundation dig an excavation pit with a minimum area of 100 x 80 cm and a min...

Page 7: ...inal assignment X1 for supply cable cable cross sections and fuse protection Performance class 3 7 kW 16 A Conduc tor Number Color L 1 brown or black N 2 blue PE 3 green yellow Supply cable NYM J 3x 1...

Page 8: ...XC ST If none of the test devices is available to you the missing tests must be performed by a Compleo specialist partner Enter the result of the test in a test report A test report can be obtained fr...

Page 9: ......

Page 10: ...All rights reserved This document may not be copied or reproduced in any form or by any means in whole or in part without written permission All illus trations in these assembly instructions serve on...