Hot pluggable Redundant Power Supply
Perform the following steps to install the hot pluggable redundant power supply option:
Table 8: Hot pluggable Redundant Power Supply
Step
Action
1.
Prepare the server for redundant power supply installation.
2.
Identify the redundant power supply bay at the back of the server.
3.
Remove the thumbscrew that secures the redundant power supply blank, and then lift the
blank form the back of the server.
4.
Slide the power supply into the power supply bay.
Apply pressure to the power supply until the release/lock lever clicks the power
supply securely into the bay.
5.
Connect the AC power cords to the new power supply.
6.
Verify that the existing power supply and the redundant power supply LEDs (located
on the back of the power supplies) are green.
5