Installing the iPatch Equipment
2–7
Task C. Mount the Panel Manager
Each rack with iPatch Panels is managed by an iPatch Manager. The iPatch
Manager
and each iPatch Panel must be connected to the rack’s panel bus. To
install the Panel Manager for each rack with iPatch Panels, perform the steps
below.
1
Make sure that the panel bus jumper is connected firmly to the PANEL BUS
jack on the back of the Panel Manager (Figure 2–5).
2
Make sure the display patch cord is securely connected to the back of the
Panel Manager housing and the side of the attached display.
Figure 2–5
Checking the Panel Bus Jumper
Check the panel bus jumper here.
Figure 2–6
Checking the Display Patch Cord
Check the display patch cord here.
Check the display patch cord here.