![CommScope ICX7400-1X40GQ Hardware Installation Manual Download Page 50](http://html1.mh-extra.com/html/commscope/icx7400-1x40gq/icx7400-1x40gq_hardware-installation-manual_2643843050.webp)
48
Ruckus ICX 7450 Switch Hardware Installation Guide
Part Number: 53-1003899-09
Installing the Ruckus ICX 7450
Attaching a PC or terminal
FIGURE 40
DC power supply wiring assembly
5.
Use the wire-tightening screws to secure the wires.
6.
Insert the earth ground wire into the ground terminal on the DC wiring assembly. Refer to
.
NOTE
This equipment installation must meet NEC/CEC Code requirements. Consult local authorities for regulations.
7.
Insert the DC power supply wiring assembly with the wires connected into the power supply and tighten the assembly screws.
Refer to
8.
Using the handle on the power supply, hold the power supply level and guide it into the carrier rails on each side of the power
supply slot. Gently push the power supply all the way into the slot, ensuring that it firmly engages with the connector.
9.
When you are sure the power supply has properly engaged the connector, tighten the chassis attachment screws to secure the
power supply in the slot.
When the Ruckus ICX 7450 is powered on, the power LED on the front of the device should turn green to confirm that the power supply
is correctly installed and supplying power. Refer to
“Ruckus ICX 7450 front-panel LEDs”
Attaching a PC or terminal
To assign an IP address, you must have access to the command line interface (CLI). The CLI is a text-based interface that can be
accessed through a direct serial connection to the device and through Telnet connections. The CLI is described in detail in the
Ruckus
FastIron Management Configuration Guide
.
Access the CLI by connecting to the console port. After you assign an IP address, you can access the system through Telnet or Ruckus
Network Advisor.
Use the following steps to attach a management station to the console port.
1
Wire-tightening screws
3
Earth ground wire
2
DC power source wires
4
Assembly screws