![CommScope FDH 3000 User Manual Download Page 49](http://html.mh-extra.com/html/commscope/fdh-3000/fdh-3000_user-manual_2643703049.webp)
ADCP-96-167 • Issue 5 • July 2016
Page 43
© 2016, CommScope, Inc.
Figure 37. Mounting Splice Chips
5. After splicing is completed, close the clear plastic cover on each splice tray.
6. Re-install the each splice tray in the cabinet. The routing for top-mounted splice
trays is shown in
and the routing for bottom-mounted splice trays is
shown in
. Avoid twisting or kinking the fiber subunit tubes. Maintain a
1.5-inch (3.81 cm) minimum bend radius for all non reduced bend radius fiber.
Figure 38. Top-Mounted Distribution Splice Tray Installation
24351-A
WISHBONE
RETAINERS
DISTRIBUTION
PORT FIBERS
DISTRIBUTION
CABLE FIBERS
COMMON
TIE POINT
DISTRIBUTION
SPLICE TRAYS (1 & 2)
HOOK AND
PILE STRAP
MAKE TWO
LOOPS AROUND
TRAY HOLDER
24363-A