Attach Drip Rail
Notch and extend Vinyl Sweep (g2) pass Drip Rail edge as shown in
figure below. Attach Drip Plugs (Z) onto Drip Rail (see exploded
view - sheet 1), be sure to remove the knockout on the hinge side
drip plug so the water will drain. Clean bottom rail of door with
alcohol to remove any oil. Failure to clean door rail prior to installa-
tion of Drip Rail (G) may cause tape to release. Remove backing
from tape and position Drip Rail flush with backside of Hinge Stile
(f2) as shown in figure below.
Sweep should cover gap at bottom of Door as shown in figure be-
low. Slightly elevate Drip Rail at strike side prior to securing to cre-
ate a sloping effect.
Glass Note:
Two (2) optional self drilling
screws (O) are provided in
case you want to further se-
cure the drip rail. If using
screws to attach drip rail . . .
never drill holes within 5/8”
of exposed glass! To do so will result in glass breakage.
Trim top & bottom Dam Strips
Measure the door opening width at Sill and Header levels. Trim top
and bottom Dam Strips (D) to measurements obtained. With high
lips toward exterior, position Dam Strips on the Header and Sill and
snap them into place.
A
D
Install Door Assembly
Insert the Door Assembly’s Hinge Post (f1) into the Post from which
it is to swing, then insert the Strike Post (J) into the post it will strike
(see exploded view - sheet 3). Magnet on door should face toward
interior when installed, while magnet on strike post should face
toward exterior.
J
L
Attach Door Handles
Attach the Door Handles (H) to the door using two(2) Door Handle
Screws (I) as shown in exploded view - sheet 3.
Secure Header
From interior, secure Header to Wall Jambs and to Corner Assem-
bly using 638THS Screws (K), see explode view - sheet 1. Screw
(K) is not self drilling, therefore, pre-drill pilot holes using a 7/64”
drill bit. To prevent glass breakage when drilling the Header, tem-
porarily slide glass panel away from Wall Jamb. When done, re-
center glass panel as before.
Leak Proof Your Installation
Run a bead of clear mildew resistant caulking down the full length of
each Wall Jamb outside where the Jambs meet the Walls. Now run
a bead outside where the Sills meets the curb. Follow caulking
manufacturer’s instructions before using shower (normally 24 hours).
Installation is now complete.
Adjust Door Assembly
Adjust Door Assembly and
Strike Post as needed for
proper Door operation.
Note: Door Assembly bottom
must always remain parallel
to Sill in order for door to
operate properly. When satisfied with door operation, secure Hinge
Post (f1) and Strike Post (J) to the vertical posts using six(6) 638PHPT
Installation Screws (X). See exploded view - sheet 3.
PARALLEL TO SILL
Insert Glazing Vinyls
Insert Vertical and Horizontal Glazing Vinyl (S & T) to secure the
Glass Panels (R & Q) in place. Use a vinyl roller to speed up
installation.
Measure, trim & position Header
Measure from walls to outside of Corner Assembly as shown
above. Trim Header pieces (B & C) to length as per “Spec #5” (see
specification table on page 2). When done trimming, position
Header on top of Jambs. Do not secure at this time.
B
E
E
C
TRIM LENGTH
GLASS
G