SAMPLE - HANDOVER REPORT
Declaration of the compliant assembly and operational handover of electric chain hoists
Installation site:
CONTRACTOR
Name:
Surname:
Person responsible:
CLIENT
Name:
Surname:
Person responsible:
The contractor hereby confirms to the client that all Lodestar D8 Plus electric chain hoists installed
by them former comply with the applicable regulations and recognized technical rules.
The required user information and proofs were provided.
Comments:
Date
Date
Signature Contractor
Signature Client
DOCUMENTATION
- Prior to each assembly, the Lodestar D8 Plus electric chain hoist
and all equipment required for operation (e.g. slings, load handler,
control system, cabling) must be visually inspected.
- The user must ensure that the results of the tests
are recorded and kept for the entire period of use.
- The documentation of the inspection must provide
at least the following information:
a) Identification of the electric chain hoist.
b) Type of inspection.
c) Date and place of the inspection.
d) Test basis.
e) Scope of testing.
f) Result of the test.
g) Evaluation of identified defects.
h) Statements for further operation.
i) Date of the next inspection.
l) Name and signature of the person qualified for the inspection.
- Records can also be kept in electronic form. If electric chain
hoists are used at different locations, proof of the performance
of the last inspection must be provided so that it can be
inspected at the place of use.
- A summary of all documents relevant to the inspection is
appropriate to illustrate the complete history of an electric
chain hoist.
- The proof of the tests can be supplemented by test labels.