6 Start-up
6.1 General
description
The indicated operations should be done by qualified technician with specific training on the product.
The electrical, water connections and the other system works are by the installer.
Upon request, the service centres performing the start-up.
Agree upon in advance the star-up data with the service centre.
For details refer to the different manual sections.
Before checking, please verify the following:
•
the unit should be installed properly and in conformity with this manual
•
the electrical power supply line should be isolated at the beginning
•
the unit isolator is open, locked and equipped with the suitable warning
•
make sure no tension is present
After turning off the power, wait at least 5 minutes before accessing to the electrical panel or any other electrical component.
Before accessing check with a multimeter that there are no residual stresses.
6.2 Preliminary
checks
Unit OFF power supply
1.
safety
access
2.
functional
spaces
3.
structure
integrity
4. unit on vibration isolators
5. unit input water shut-off valves for cleaning
6. vibration isolators on water connections
7. expansion tank (indicative volume = 5% system content)
8. minimum system water content
9.
cleaned
system
10. loaded possible glycol so corrosion inhibitor
11. system under pressure
12.
vented system
13. refrigerant circuit visual check
14.
earthing connection
15. power supply features
16. electrical connections provided by the customer
6.3 Start-up
sequence
Unit ON power supply
1. compressor crankcase heaters operating at least since 8 hours
2. off-load voltage measure
3. phase sequence check
4. pump manual start-up and flow check
5. shut-off valve refrigerant circuit open
6.
unit
ON
7. load voltage measure and absorptions
8. liquid sight glass check (no bubbles)
9. measure return and supply water temperature
10. measure super-heating and sub-cooling
11. check no anomalous vibrations are present
12. climatic curve personalization
13. climatic curve personalization
14.
scheduling personalization
15. complete and available unit documentation
Summary of Contents for WSH-XEE2 10.2
Page 7: ...M08P40G16 00 WSH XEE2 10 2 120 2 7 2 3 Instructions for disassembly Only with options MOBMAG...
Page 14: ...14 WSH XEE2 10 2 120 2 M08P40G16 00 5 5 Connections performer by customer EXH O 8 6...
Page 43: ...M08P40G16 00 WSH XEE2 10 2 120 2 43 9 3 Source side 3 way modulating valve...
Page 44: ...44 WSH XEE2 10 2 120 2 M08P40G16 00 9 4 Source side 2 way modulating valve...
Page 45: ...M08P40G16 00 WSH XEE2 10 2 120 2 45 9 5 VALVE FOR DOMESTIC HOT WATER...
Page 63: ...Page intentionally left blank...