Installation:

 

The LP Cleverfit Pro can be installed either Ceiling or Wall Mounted. The LP Cleverfit 

Pro uses a “slide 

connect bracket base” that is mounted and wired into position first. The main body can be installed once 
the base is wired or later to avoid damage during the construction phase. Please follow the steps below 
to install the LP Cleverfit Pro Exit: 
 

 

Disengage the slide connect bracket from the exit body. Position the base in the mounting position.  

 

Using the bracket as a guide, mark 2 holes for mounting and one for mains access. Then install the 
bracket using appropriate fixings (not supplied). 

 

Configure all the mounting parts and cable entry points as below (if required) and engage the body 
into the slide connect bracket. Connect mains and check that the LP Cleverfit Pro Exit is 
Operational

 

If the CTP capabilities are activated, please affix the CTP status label to a visible surface and Four 
Segment Marking on the p

roduct will include an ‘’F’’ in third segment block. 

 
Networking: 

When installing the product on a monitored network, (ZONEWORKS, HIVE, DATA, DALI) simply insert 
the relevant Smart Node PCA. 

Dimensions: 

Testing:

 

Once connected to the 240V mains supply, the unit must be allowed to charge the battery for at least 24 
hours. Conduct the following tests: 
 

 

For the first test, the emergency lamp must remain illuminated for at least 2 hours after disconnection 
from the mains supply. 

 

 

Subsequent tests  require  the  unit  to  illuminate  for  at  least  90  minutes. The  results  of  all tests  are 
required to be recorded in a service logbook, which is to be kept on-site at all times. If the unit fails 
to remain illuminated for the requisite time, remedial action must be taken to repair the situation and 
once completed, the unit must pass a subsequent test. For more specific information, please refer to 
the current edition of the AS/NZS 2293.2 and AS/NZS 60598.2.22 Standards. 

 

 

Clevertronics recommend scheduled PCA LED Light and battery changes at 4 yearly intervals or as 
determined by regular testing. 

 

Trouble Shooting: 

Below are a list of common problems and their possible causes. 

 
Fault:  

The Green LED Test Switch indicator is not illuminated.

 

Check:   A.C. is connected and is turned on. 
 

Battery is connected 
Test Switch for damage. 
 

Fault:  

Lamp does not illuminate in emergency mode. 

 

Check:   A.C. is connected. 
 

Lamp is correctly inserted. 

 

Battery is connected 

 

Fault:  

Lamp illuminates in emergency mode, but only stays on for a short period. 

Check: 

Battery has been allowed to charge for at least 24 hours. 

 

Battery for damage. 

 

 

Rated Emergency Lumen Output in accordance with AS2293.1, not applicable 
for 

–TH (theatre) version (refer to spacing tables for installation positions): 

 

 

 

Refer to the Technical Label for classification information.

 

Caution:

 

On many building sites, power circuits may be cut off in an uncontrolled and repetitive basis during 
construction. As a result, any Exit & Emergency Units, on these circuits, will have their batteries 
discharged or “cycled”. The battery in this fitting has been selected to give excellent long-life 
performance in a controlled AS2293 testing environment. Excessive battery cycling will reduce through-
life performance and may lead to premature battery failure. Battery warranty claims, as a result of such 
abuse, are specifically EXCLUDED from Clevertronics warranty terms. 

Warranty:

 

For Product Warranty information and Terms and Conditions of Sales please refer to our website 

http://clevertronics.com.au/terms-conditions-sale-australia-nz/

 

 

 

Reviews: