CLEVELAND RANGE SEL-R
SEQUENCE OF OPERATIONS
When using these instructions refer to the SEL-R wiring schematic.
1.
Supply Voltage is sent to the normally open contacts of the element contactor
2.
Supply Voltage is sent through the 1.5 amp fuse to the power switch
3.
With the power switch in the on position, supply voltage is sent to the primary of the
main transformer.
4.
120 VAC is sent from pins 1 and 2 on the secondary of the main transformer through
the 1 amp fuse to the tilt interrupter switch.
•
If the skillet is in the down position 115 VAC is sent from the interrupter switch
through the high limit to pin 9 on the thermostat.
5.
When the thermostat is calling for heat 115 VAC is sent to the coil of the element
contactor.
•
The normally open contacts of the element contactor close sending supply voltage
to the elements.
•
The elements will heat the skillet until the thermostat is satisfied.
6.
When the thermostat is satisfied 115VAC is removed from pin 10 and the heat circuit
is de-energized.
7.
If the skillet is equipped with the optional Power Tilt, 24 VAC is sent from terminals
3 and 4 of the secondary of the main transformer through the 15-amp fuse to the
bridge rectifier
8.
The AC current is rectified to DC voltage that is then filtered by the capacitor and
resistor and sent to the tilt switch.
9.
When the switch is in the up position the DC motor is energized and the actuator
extends.
10.
When the switch is in the down position the polarity is reversed and the motor is
energized to retract the actuator.