ClearFire

®

 

Model CFH

Horizontal Steam Boiler

Startup Guide

750-293

Summary of Contents for ClearFire SFH

Page 1: ...www cleaverbrooks com ClearFire Model CFH Horizontal Steam Boiler Startup Guide 750 293...

Page 2: ...essure testing of that system at test pressures in excess of 1 2 psi 3 5 kPa DANGER WARNING Should overheating occur or the gas supply valve fail to shut off do not turn off or disconnect the electric...

Page 3: ...voltage ignition transformers Control panel must be connected to earth ground For electrical wiring requirements see wiring diagram provided with the boiler or in the CFH manual Figure 1 CFH Connecti...

Page 4: ...re to be connected to the ClearFire boiler Refer to flue piping manufacturer for proper installation and sealing instructions See also Chapter 3 in the CFH Operation and Maintenance manual 1 4 Boiler...

Page 5: ...in power 115 VAC single phase 60Hz and any remote wiring should be brought to the left side of the control panel and terminated at the appropriate terminals provided Controls for the boiler feed pump...

Page 6: ...e Figure 5 include the following Combustion Air Proving Switch Low Gas Pressure Switch High Gas Pressure Switch Dual Safety Shut off Valve SSOV Depress all manual reset buttons for all controls prior...

Page 7: ...not close the vent valve until water is visible in the gauge glass The feed pump will shut off when water reaches the Pump Off probe level Check to ensure that no leaks appear at any pipe connections...

Page 8: ...pre configured with default parameter settings for the Model CFH Prior to starting the boiler verify that the factory default settings are correct for your application See the boiler operation manual...

Page 9: ...igure 12 Operation screen 2 3 4 To change the steam pressure setpoint 1 Press the yellow highlighted setpoint display window 2 Clear the current value 3 Enter the desired value 4 Press OK 1 Note Some...

Page 10: ...ble and attempt to start the burner The CB Falcon should lock out indicating Lockout 109 Ignition Failure Reconnect flame rod cable after test The CB Falcon requires a manual reset to resume operation...

Page 11: ...manual for boil out procedure 5 LOCKOUTS HOLDS AND ALERTS To assist in monitoring boiler operation the CB Falcon control system employs messages of three types Lockouts Holds and Alerts Lockouts and...

Page 12: ...Figure 15 Press this banner to access the Alert or Lockout History where a list of the most recently occurring Alerts Lockouts can be viewed To obtain more information for a particular message press t...

Page 13: ...CFH Startup Guide Part No 750 293 13 Figure 16 CFH Wiring Diagram...