22-27
Cisco ONS 15454 Procedure Guide, R5.0
October 2005
Chapter 22 DLPs A500 to A599
DLP-A530 Install the Tie-Down Bar
DLP-A530 Install the Tie-Down Bar
Step 1
Align the ends of the tie-down bar with the four screw holes located 1 rack unit (RU) below the
ONS 15454.
shows the tie-down bar, the ONS 15454, and the rack.
Figure 22-9
Tie-Down Bar
Step 2
Install the four screws into the rack.
Step 3
Return to your originating procedure (NTP).
Purpose
This task installs the tie-down bar used to secure cabling on the rear of the
ONS 15454. The tie-down bar can be used to provide a diverse path for
redundant power feeds and cables.
Tools/Equipment
Tie-down bar
Screws (4)
Prerequisite Procedures
DLP-A5 Mount the Shelf Assembly in a Rack (One Person), page 17-5
DLP-A6 Mount the Shelf Assembly in a Rack (Two People), page 17-6
Required/As Needed
As needed
Onsite/Remote
Onsite
Security Level
None
105012
Tie-down bar
Summary of Contents for ONS 15454 Series
Page 28: ...Tables xxviii Cisco ONS 15454 Procedure Guide R5 0 December 2004 ...
Page 44: ...Tasks xliv Cisco ONS 15454 Procedure Guide R5 0 December 2004 ...
Page 53: ...liii Cisco ONS 15454 Procedure Guide R5 0 December 2004 About this Guide Document Conventions ...
Page 55: ...lv Cisco ONS 15454 Procedure Guide R5 0 December 2004 About this Guide Document Conventions ...
Page 850: ...Index IN 22 Cisco ONS 15454 Procedure Guide R5 0 December 2004 description 4 11 remove 18 23 ...