19-46
Cisco ONS 15454 Procedure Guide, R5.0
September 2005
Chapter 19 DLPs A200 to A299
DLP-A264 Provision a J1 Path Trace on Circuit Source and Destination Ports
Note
Cisco recommends that you set the DRI port HOT value to zero and the circuit path selector HOT value
to a number equal to or greater than zero.
Step 1
From the View menu, choose
Go to Network View
.
Step 2
Click the
Circuits
tab.
Step 3
Click the path protection circuit you want to edit, then click
Edit
.
Step 4
In the Edit Circuit window, click the
UPSR Selectors
tab.
Step 5
Create a hold-off time for the circuit source and destination ports:
a.
In the Holder Off Timer area, double-click the cell of the circuit source port (top row), then type the
new hold-off time. The range is 0 to 10,000 ms in increments of 100.
b.
In the Hold-Off Timer area, double-click the cell of the circuit destination port (bottom row), then
type the hold-off time entered in Step
Step 6
Click
Apply
, then close the Edit Circuit window by choosing
Close
from the File menu.
Step 7
Return to your originating procedure (NTP).
DLP-A264 Provision a J1 Path Trace on Circuit Source and Destination Ports
Note
This task assumes you are setting up path trace on a bidirectional circuit and setting up transmit strings
at the circuit source and destination.
Step 1
From the View menu, choose
Go to Network View
.
Step 2
Click the
Circuits
tab.
Step 3
For the STS circuit you want to monitor, verify that the source and destination ports are on a card that
can transmit and receive the path trace string. See
for a list of cards.
Purpose
This task creates a path trace on STS circuit source ports and destination
ports or a VCAT circuit member.
Tools/Equipment
ONS 15454 cards capable of transmitting and receiving path trace must be
installed at the circuit source and destination ports. See
for a list of cards.
Prerequisite Procedures
DLP-A60 Log into CTC, page 17-66
Required/As Needed
As needed
Onsite/Remote
Onsite or remote
Security Level
Provisioning or higher
Summary of Contents for ONS 15454 Series
Page 28: ...Tables xxviii Cisco ONS 15454 Procedure Guide R5 0 December 2004 ...
Page 44: ...Tasks xliv Cisco ONS 15454 Procedure Guide R5 0 December 2004 ...
Page 53: ...liii Cisco ONS 15454 Procedure Guide R5 0 December 2004 About this Guide Document Conventions ...
Page 55: ...lv Cisco ONS 15454 Procedure Guide R5 0 December 2004 About this Guide Document Conventions ...
Page 850: ...Index IN 22 Cisco ONS 15454 Procedure Guide R5 0 December 2004 description 4 11 remove 18 23 ...