  Opening the Chassis

Caution

When installing the PoE card, ensure that the card is installed in the proper direction. Improper 
installation will damage the PoE card. Installation of the PoE card requires the installation of three metal 
standoffs, to which the card is then secured by using three screws. Be sure to use all three screws to 
ensure that the card is installed properly.

Tip

If the card is not installed in the correct direction, the three screw holes will not match up with the three 
metal standoffs.

Step 5

Place the PoE card on top of the three metal standoffs, lining up the screw holes in the PoE card with the 
metal standoffs.

Step 6

Push the PoE card down towards the system board until it is firmly fixed into the PoE connector.

Step 7

Insert the screws provided in the accessory kit through the PoE card and into the metal standoffs. See 

Figure 5

. Carefully tighten the screws with a Phillips screwdriver.

Step 8

Close the router (see 

Closing the Chassis, page 10

), and then connect the PoE power supply to an AC 

power outlet. To connect the PoE power supply to an AC power outlet, see the 

Cisco 860 Series, 

Cisco 880 Series, and Cisco 890 Series Hardware Installation Guide, Connecting Power over Ethernet

.

Opening the Chassis

To open the chassis, you will need a number-2 Phillips screwdriver, a wrist strap, and an antistatic mat.

Warning

During this procedure, wear grounding wrist straps to avoid ESD damage to the card. Do not directly 
touch the backplane with your hand or any metal tool, or you could shock yourself. 

Statement 94

Follow these steps to open the chassis:

Step 1

Disconnect the power supply cable.

Step 2

Disconnect all cables from the router back panel.

Step 3

Use the number-2 Phillips screwdriver to remove the screws at the middle on the back panel, and at the 
sides of the router. 

Figure 6

 shows the location of the screws. The screws are in the same location on all 

Cisco 880 series ISRs. 

Summary of Contents for 880 Series

Page 1: ...ns Safety Warnings Installing Main Memory Installing Power Over Ethernet Opening the Chassis Closing the Chassis Note Memory and PoE are the only upgradable options in the Cisco 880 series and Cisco 890 series ISRs Do not remove or install any other internal module Safety Warnings Warning This equipment must be grounded Never defeat the ground conductor or operate the equipment in the absence of a...

Page 2: ...s are present in WAN ports regardless of whether power to the unit is OFF or ON To avoid electric shock use caution when working near WAN ports When detaching cables detach the end away from the unit first Statement 1026 Installing Main Memory This section contains the following information Items Shipped Installation Procedure Items Shipped Table 1 shows the items shipped with a DIMM unit Installa...

Page 3: ...ices Routers OL 16194 01 Installing Main Memory Figure 1 DIMM Socket Location Step 3 Remove any existing DIMM by gently pulling the spring loaded clips on the end of the socket far enough to release the DIMM then gently pulling the DIMM up and away from the socket See Figure 2 1 DIMM socket 27049 6 1 ...

Page 4: ...he DIMM into the DIMM socket at a 45 degree angle as shown in Figure 3 Figure 3 Installing a DIMM Step 5 Gently push the DIMM down toward the system board as shown in Figure 3 until it snaps into the spring loaded clips Step 6 Close the chassis according to the instructions in Closing the Chassis section on page 10 1 Spring loaded clips 3 DIMM socket 2 DIMM 103155 1 2 3 1 DIMM 3 Spring loaded clip...

Page 5: ...erminals Avoid using such interconnection methods unless the exposed metal parts are located within a restricted access location and users and service people who are authorized within the restricted access location are made aware of the hazard A restricted access area can be accessed only through the use of a special tool lock and key or other means of security Statement 1072 To install the power ...

Page 6: ...ree metal standoff holes on the system board See Figure 4 for the location of the PoE connector Two standoff holes are identified by a star pattern surrounding the hole the third hole has a screw attached to it Figure 4 PoE Connector Step 3 Remove the screw from the third standoff hole 1 PoE connector 3 Standoff hole with screw 2 Standoff holes with star pattern 24197 9 1 3 2 ...

Page 7: ... one notch into the third standoff hole Use a 1 4 inch nut driver to tighten the standoff with one notch and a 3 16 inch nut driver to tighten the standoffs with two notches Caution Make sure that the standoffs are straight when installed Tighten them gently but firmly The shoulder of each standoff must be seated tightly against the system board Figure 5 Installing the Power over Ethernet Card 1 S...

Page 8: ...ry kit through the PoE card and into the metal standoffs See Figure 5 Carefully tighten the screws with a Phillips screwdriver Step 8 Close the router see Closing the Chassis page 10 and then connect the PoE power supply to an AC power outlet To connect the PoE power supply to an AC power outlet see the Cisco 860 Series Cisco 880 Series and Cisco 890 Series Hardware Installation Guide Connecting P...

Page 9: ...sis Screws Locations Step 4 Place your hand on both sides of the router where the screws were located With your fingers gently pry the chassis cover outward and away from the router and lift the chassis cover up The front end of the chassis cover will remain attached to the chassis Figure 7 shows how to open the chassis 1 Locations of the screws 241976 1 1 1 ...

Page 10: ...hassis Step 5 Place the router bottom on an antistatic mat Closing the Chassis To close the chassis you will need a number 2 Phillips screwdriver and a wrist strap Warning During this procedure wear grounding wrist straps to avoid ESD damage to the card Do not directly touch the backplane with your hand or any metal tool or you could shock yourself Statement 94 241977 ...

Page 11: ...Catalyst CCDA CCDP CCIE CCIP CCNA CCNP CCSP CCVP Cisco the Cisco Certified Internetwork Expert logo Cisco IOS Cisco Lumin Cisco Nexus Cisco Press Cisco Systems Cisco Systems Capital the Cisco Systems logo Cisco Unity Collaboration Without Limitation Continuum EtherFast EtherSwitch Event Center Explorer Follow Me Browsing GainMaker iLYNX IOS iPhone IronPort the IronPort logo Laser Link LightStream ...

Page 12: ...12 Installing Memory and Power Over Ethernet in Cisco 880 Series and Cisco 890 Series Integrated Services Routers OL 16194 01 Closing the Chassis 2009 Cisco Systems Inc All rights reserved ...

Reviews: