DANGER
: Injuries and/or material damages
can occur with overpressure when testing
watertight!
High pressure can damage regulatory and
safety devices and reservoir.
After filling with water set the boiler on
pressure that is equal to the opening
pressure of safety valve
Comply with maximum pressure of
installed components
After testing sealing, open again closing
valves
Make sure that all pressures, regulatory
and safety parts work correctly
DANGER:
Health threat due to mix of drinking
water!
It is demanding to respect state norms and
regulations on avoiding mix drinking water
(with water from heating installations)
Comply with EN 1717
NOTE:
Installation damage due to bad quality
of water! Heating installation can be damaged
by corrosion or scale depending on water
characteristics.
Comply with filling requests for water
according to VDI 2035 or project
documentation and catalogue
NOTE:
Material damage due to temperature
tension.
If you fill the boiler in hot condition,
temperature tension can cause cracks
due to tensions. Boiler will start to leak
Fill the boiler only in cold condition
(temperature of empty duct can be max
40 °C)
Fill the boiler only through quick valve on
pipe installation (return line) of the boiler
4.7
Filling the installations and watertight
testing
The eBasic boiler does not contain a manometer, so
when filling the installation with water, the pressure must
be monitored on the manometer installed on the heating
installation
.
4.7.1 Filling the boiler with heating water and
sealing test
Waterproof should be tested prior to put on the boiler.
The installation should be vented via valves on the
radiators
Open the filling and emptying tap
Slowly fill the boiler. In doing so, monitor the increase in
pressure
When the operating pressure is reached, close the tap.
Bleed the installation via the valve on the radiator
When the operating pressure drops by venting, the water
must be topped up
Carry out a leak test in accordance with local regulations
After testing for leaks, open any items that have closed
due to filling
Check that all safety components are working properly
If the boiler has been tested for leaks and no leaks have
been observed, set the correct operating pressure
Remove the hose from the filling and emptying tap
Enter the operating pressure and water quality values in
the Operating Instructions
During the first filling of repeated filling or when change
the water
Comply with requests for filling water
4.7.2 Heating pump air emission and de-blocking
This device does not have a circulating pump in it.
When the external heat pump is blocked, do the following:
•
Carefully try to unlock the pump shaft with a suitable
screwdriver
4.7.3 Boiler and installation air emission
• This unit does not have built-in venting.
• Ventilation must be installed on the installation.
Installation
Summary of Contents for El-Cm eBasic 12kW
Page 19: ...Electric connecting Image 12a Boiler electric scheme eBasic with nominal power of 6kW...
Page 20: ...Electric connecting Image 12b Boiler electric scheme eBasic with nominal power of 9kW and 12kW...
Page 21: ...Electric connecting Image 13a Boiler electric scheme eBasic with nominal power of 18kW...
Page 22: ...Electric connecting Image 13b Boiler electric scheme eBasic with nominal power of 24kW...