Concrete Patio Stone

Concrete Slab Foundation

Foundation Options

Concrete Slab Foundation (Option 2)
Typically a slab 3"-4" thick laid over a subbase of 4" of gravel or crushed rock is sufficient but may vary (consult

your local Cedarshed supplier). Either mix your own concrete or have it delivered to your site. A 10' x 10' x 4" slab
will require approximately 1 cubic yard of concrete. In any case, make sure you excavate the slab area to a depth
of 6", use 4" of gravel as your subbase, Welded Wire Mesh as reinforcing (optional) and 4" of concrete (trowel to
allow for drainage away from the center high point).

WHAT TYPE OF FOUNDATION SHOULD I USE?

Concrete Patio Stone Foundation (Option 1):

If the ground is stable and has sufficient drainage, you can set patio stones directly on firm compacted soil. If not, lay

the Patio Stones on gravel or crushed rock. Place the Patio Stones at the load bearing points of the floor and under
each doorway post. You may wish to slide the exterior Patio Stones a few inches under the Floor Joist System to

reduce a tripping hazard.

WHAT SHOULD I DO TO PREPARE THE SITE?

Before you begin assembly, clear the construction area. Remove all debris; roots, grass, rocks etc. Make sure the

ground slopes away from the site at least 10 feet in all directions. If necessary, build up the soil in the center of the
site and slope away from the high point to provide drainage. Fill in any low spots within the perimeter of the site.
GRADE A SLOPE OF 1/8" PER FOOT, enough to prevent water accumulation. We recommend excavating the
site 4" deep and laying gravel or crushed rock where drainage may be a concern.

With all of the Patio Stones in place, you are now ready to level the Patio Stone Foundation.

Using a shovel, add or remove soil beneath each Patio Stone to adjust the level. Use a carpenters level on a long

straight piece of lumber on end to level from one Patio Stone to another for all the Patio Stones. Remember to
compact (soil/sand/gravel) as much as possible under each Patio Stone. It is recommended that you level the
outside Patio Stones first and then work your way inward.

THE CONSTRUCTION OF 'THE GARDEN SHED' MUST BE DONE ON A LEVEL FOUNDATION AND BE IN ITS FINAL

LOCATION. PLACE ADDITIONAL FOUNDATION PADS AS YOU FEEL NECESSARY TO STABILIZE THE FLOOR

SYSTEM. YOU MUST HAVE A LEVELED FOUNDATION BEFORE PROCEEDING TO LAY FLOOR ASSEMBLY.

Refer to following sheets for dimensions

Foundation (Option 1)

(Option 2)

Floor Decking not  shown

B83DD

Summary of Contents for Bayside B83DD

Page 1: ...B83DD Issue 01 1 Nov 21 ...

Page 2: ...esponsibilty of the purchaser Please visit our website at www cedarshed com for additional safety tips and other considerations to promote safe and enjoyable usage of your Cedarshed Product for years to come NOTE Garden tools for foundation leveling work Power drill drill bits 4 Step ladders 8 Min 36 carpenters Level Hammer saw tape measure pencil etc 1 16 drill bit B83DD 1 tube of outdoor rated l...

Page 3: ...ble to keep the should be abided by If the structure is elevated above ground local Building Code requirements are solely the owners responsibility and snow off the roof Roof Snow Load Ratings vary by geographical location If a heavy or wet snowfall occurs it is advisable to clear the Some Safety Tips to Consider Include reference for future maintenance residential use Please follow the Assembly M...

Page 4: ...ll Top Skirting Gable Fascia Gable Fascia Bottom Skirting Wall Panels Wall Headers Wall Panel Bottom Skirting Trim 1 x 3 1 4 x 87 1 2 Trim 1 x 3 x 79 Top Plate Trim 1 x 1 x 79 Trim 1 x 2 x 87 1 2 1 x 2 x 87 Trim 1 x 2 x 80 Trim Trim 1 x 2 x 87 1 2 Fascia Boards Cedarshed Plaque B83DD Middle Skirting Top Door Trim Wall Header Wall Door Frame with Trim Header 2ea 2x3x65 Skirting Skirting Skirting Sk...

Page 5: ... Double Door Your Cedarshed Product is constructed of Western Red Cedar Exterior Wall and Roof framing is 2 x 3 SPF Floor is 2 x 4 Cedar with 5 8 plywood A C B SIDE VIEW D Area 23 5 Sq Ft 98 31 1 16 x 71 3 4 x 2pcs 34 1 2 D B83DD 702 lbs 84 94 3 4 Issue 01 1 Nov 21 ...

Page 6: ...n door is located on 4ft side ACCESSORIES FASTENERS DOOR HARDWARE B83DD Barrel bolt To confirm you have received all materials sort them according to this list Call or e mail us if you are missing any items and we will courier or ship as soon as possible Toll Free Customer Support Line 1 800 830 8033 E mail sales cedarshed com Protect your building materials from wet weather by covering them when ...

Page 7: ... construction area Remove all debris roots grass rocks etc Make sure the ground slopes away from the site at least 10 feet in all directions If necessary build up the soil in the center of the site and slope away from the high point to provide drainage Fill in any low spots within the perimeter of the site GRADE A SLOPE OF 1 8 PER FOOT enough to prevent water accumulation We recommend excavating t...

Page 8: ...der Door Post Foundation Plan Concrete Patio Stone Foundation Option 1 12 x 12 305 x 305 Concrete Slab Foundation Option 2 34 1 2 x 98 978 x 2 490 Under Floor Joist System Metric Dimensions shown in brackets B83DD Floor Joist System ...

Page 9: ... P11 FIG P11 1 9 FIG P11 3 FIG P11 2 3 Screw Can Be Brown Green B83DD Part Number Description Size or Type of Pcs CODE P 2423 Floor joist 2 x 4 x 23 3 P 2423 P 2434G 4 P 2469 3 P 2469 P PL I1734G Plywood sheet 5 8 x 17 x 34 1 FLOOR PARTS 3 Floor joist Floor joist 2 x 4 x 34 2 x 4 x 69 Plywood sheet 5 8 x 27 x 34 P PL I2734G Issue 01 1 Nov 21 P PL I1734G P PL I2734G P 2434G P 2469 P 2434G ...

Page 10: ...ng 2 3 screws per joist Assembly the joist box together as per Fig P12 2 The completed joist box is pictured in Fig P12 3 34 1 2 x 26 Joist Box P12 FIG P12 1 10 FIG P12 3 FIG P12 2 B83DD 3 Screw Can Be Brown Green P 2434G P 2423 Issue 01 1 Nov 21 ...

Page 11: ...F 2 FIG F 3 11 FIG F 4 FIG F 2 B83DD FIG F 1 Affix the plywood panels as per Fig F 3 using 2 screws on 12 centers and affixing the plywood to each row of joist The finished floor is shown in Fig F 4 P11 P12 1 48 x 34 1 2 Plywood 1 24 x 34 1 2 Plywood 1 26 x 34 1 2 Plywood Issue 01 1 Nov 21 ...

Page 12: ...DD P 2334G BW 002 P 2346G P 2346G BW 002 BW 003 BW 003 Siding must not be sitting on the floor panel it should be on the outside as shown Wall panel frame must be flush with floor panel 3 screws between wall studs Part Number Description Size or Type of Pcs CODE WALL PARTS AND PANELS P 2313K DF 012 DF 008 DF 008 C BW 001 BW 001 DR 001 DR 001 P 2346G Headers 2 x 3 x 46 1 2 2 BW 002 Solid Wall Panel...

Page 13: ...l 5 3 screws alternating from both sides Continue installing all panels except for the door panel using 5 3 screws to attach each of the panels together and 3 3 screws to attach to the floor B83DD 5 3 screws Screw pattern wall to wall and to floor Issue 01 1 Nov 21 ...

Page 14: ...1 8 3mm gap at the top of the door middle and of the non hinge vertical edge of the door See Figure 8 below for details These gaps will allow the door to open freely Use the 1 16 drill bit to pre drill the holes before installing the hinges B83DD Fasten the hinges as shown with black screws supplied 1 8 gap OUTSIDE VIEW Door Frame C DF 012 Door Frame C DF 008 1 8 gap 1 8 gap Issue 01 1 Nov 21 ...

Page 15: ...S12 and FIGURE S13 Use 2 3 screws to attach gable and infill walls together at each joint and use 3 3 screws to attach each gable and infill wall to top of the walls 3 screws at 16 centers Attach the Roof Gables and Infill Walls with 18 3 screws B83DD P 2326C P 2326C P 2371K P 2371K P 2329G P 2329G GW 006 GW 006 IW 006 IW 006 Part Number Description Size or Type of Pcs CODE P 2371K Top plates 2 x ...

Page 16: ...y FIRST ROOF PANEL PUSHED INTO PLACE Adhesive between rafters and on seat cut to top plate Secure the roof panel using 3 screws as shown 2x3 roof rafter 1x3 top plate 2x3 wall header 2x3 wall stud Cedar bevel siding 3 long screw at each center rafter at an angle through 2x3 header and into rafter FIGURE S15 Using 3 screws affix the roof rafters to the top plates of the front and back walls See Fig...

Page 17: ...of cedar shingles up the full length of the Roof Joint Seam When complete take the Metal Flashing Shingles and slide them one by one between the rows of Cedar Shingles along the Roof Panels Joints FIGURE S15 B83DD H M FLASS H M FLASS Issue 01 1 Nov 21 ...

Page 18: ...LIED TO THE SEAMS BETWEEN WALL PANELS THIS HELPS TO KEEP ANY WATER OUT THAT MAY SOAK IN UNDER THE TRIM BOARDS 4 Here is the order they should be applied Depending on the choice of the door location there may be some trimming of the trim boards required Altering trim boards if door is on the 4 ft 1219mm narrow side of the high wide side of the shed 5 1 1 x 2 x 87 1 2 P 1287G trim board needs to be ...

Page 19: ...ce of the bevel siding and through the bottom of the skirting piece as shown on diagram C Slide in the skirting behind the bevel siding as shown on diagram B Pry the last horizontal bevel siding piece on the bottom of the gable panel slightly Do not use too much force or the bevel siding will break Bevel siding Skirting Nails 19 B83DD ...

Page 20: ...r of each soffit attach the soffit to the underside of the rafter ends For details refer to Figure S20 below FIGURE S17 2 pieces of 1 2 x 4 x 37 Soffit at each end P G437 B83DD 1 piece of 1 2 x 4 x 24 Soffit at middle P G424 Part Number Description Size or Type of Pcs CODE P G437 Soffit x 4 x 37 2 P G437 P G424 Soffit 1 P G242 x 4 x 24 SOFFITS Issue 01 1 Nov 21 ...

Page 21: ... P B G445 SKIRTING P B G633 Skirting 1 2 x 6 x 33 4 P B G633 1 2 x 6 x 12 1 4 Bottom Skirting P B G612C P B G412C Top Skirting 2 P B G412C 1 x 4 x 12 1 4 1 x 4 x 67 Door Trim P 1467 1 x 4 x 12 1 4 Top Skirting P B G412C P 1467 P B G612C Bttm Skirting 2 P B G612C 1 x 6 x 12 1 4 1 2 x 6 x 12 1 4 Bottom Skirting P B G612C 1 2 x 6 x 33 Skirting P B G633 Skirting Skirting 1 2 x 3 x 45 1 2 x 2 1 2 x 45 ...

Page 22: ...ASCIA P 1442 P 1424 P 1455Yg Fascia Fascia Gable Fascia L R 1 x 4 x 42 1 x 4 x 24 1 x 4 x 42 4 2 2 P 1442 P 1424 P 1455Yg 1 x 3 x 87 Trim P 13C87G 1 x 2 x 87 Trim P 1287G 1 x 3 x 87 Trim P 13C87G 1 x 2 x 80 Trim P 1280G 1 x 2 x 87 Trim P 1287G 1 x 3 x 79 Corner Trim P 13C79C 1 x 2 x 80 Trim P 1280G 1 x 2 x 87 Trim P 1287G 1 x 3 x 79 Corner Trim P 13C79C Issue 01 1 Nov 21 P 280G Trim 1 x 2 x 80 1 2...

Page 23: ...Pre drill the holes before mounting the handles and hasp using 1 16 drill bit 23 FIGURE S22 Handle Hasp B83DD P H DHAND P H HASP OUTSIDE VIEW Not exactly as shown Issue 01 1 Nov 21 Barrel bolt P H BBL4 ...

Page 24: ...24 Attach plaque with finishing nails Rectangle shape plaques is attached to front fascia See Figure S24 B83DD 2 finishing nails Cedarshed plaque Front fascia FIGURE S24 H PLAQL ...

Page 25: ...our finished Cedarshed product we will send you a personalized plaque free of charge that you can mount on your building max 36 letters Don t forget to enter our Best Picture Contest Refer to Questionaire for details Please refer to the questionnaire or call Cedarshed if you require additional information TOLL FREE CUSTOMER SUPPORT 1 800 830 8033 e Mail sales cedarshed com Visit our Website www ce...

Reviews: