![Carrier GAS FURNACE 58MTA Installation, Start-Up, And Operating Instructions Manual Download Page 15](http://html.mh-extra.com/html/carrier/gas-furnace-58mta/gas-furnace-58mta_installation-start-up-and-operating-instructions-manual_2562952015.webp)
Step 3—Hazardous Locations
FIRE, EXPLOSION, INJURY OR DEATH HAZARD
Improper location or inadequate protection could result in fire
or explosion.
When the furnace is installed in a residential garage, the
burners and ignition sources must be located at least 18 in.
above the floor. The furnace must be located or protected to
avoid physical damage by vehicles. When the furnace is
installed in a public garage, airplane hangar, or other building
having a hazardous atmosphere, the furnace must be installed
in accordance with the NFGC or NSCNGPIC. (See Fig. 16.)
INSTALLATION
Step 1—Leveling Legs (If Desired)
When furnace is used in upflow position with side inlet(s), leveling
legs may be desired. (See Fig. 17.) Install field-supplied,
corrosion-resistant 5/16-in. machine bolts and nuts.
NOTE:
The maximum length of bolt should not exceed 1-1/2 in.
1. Position furnace on its back. Locate and drill a 5/16-in.
diameter hole in each bottom corner of furnace. (See Fig. 17.)
Holes in bottom closure panel may be used as guide locations.
2. For each hole, install nut on bolt and then install bolt and nut
in hole. (Install flat washer if desired.)
3. Install another nut on other side of furnace base. (Install flat
washer if desired.)
4. Adjust outside nut to provide desired height, and tighten inside
nut to secure arrangement.
NOTE:
Bottom closure must be used when leveling legs are used.
See Bottom Closure Panel section.
Step 2—Installation in Upflow and Downflow
Applications
NOTE:
For downflow applications, this furnace is approved for
use on combustible flooring when special base (available from
manufacturer) Part No. KGASB0201ALL is used. Special base is
not required when this furnace is installed on manufacturer’s Coil
Assembly Part No. CD5 or CK5, or Coil Box Part No. KCAKC is
used.
1. Determine application being installed from Table 1.
2. Construct hole in floor per dimensions specified in Table 1
and Fig. 18.
3. Construct plenum to dimensions specified in Table 1 and Fig.
18.
4. If downflow subbase (KGASB) is used, install as shown in
Fig. 19. If Coil Assembly Part No. CD5 or CK5 or Coil Box
Part No. KCAKC is used, install as shown in Fig. 20.
NOTE:
Remove furnace perforated, supply-air duct flanges when
they interfere with mating flanges on coil or downflow subbase. To
remove perforated, supply-air duct flanges, use wide duct pliers,
duct flange tool, or hand seamers to bend flange back and forth
until it breaks off. Be careful of sharp edges. (See Fig. 21.)
Fig. 16—Installation in a Garage
A93044
18-IN. MINIMUM
TO BURNERS
Fig. 17—Leveling Legs
A89014
1
3
⁄
4
″
1
3
⁄
4
″
1
3
⁄
4
″
1
3
⁄
4
″
5
⁄
16
″
5
⁄
16
″
5
⁄
16
″
5
⁄
16
″
Fig. 18—Floor and Plenum Opening Dimensions
A96283
PLENUM
OPENING
C
A
B
D
FLOOR
OPENING
15
→