37
Fig. 42 — 23XRV Frame Size B Machine Footprint
Fig. 43 — Standard Isolation
INSTALL ACCESSORY ISOLATION (IF REQUIRED)
Uneven floors or other considerations may dictate the use of ac-
cessory soleplates (supplied by Carrier for field installation) and
leveling pads. Refer to Fig. 44.
Level machine by using jacking screws in isolation soleplates. Use
a level at least 24 in. (610 mm) long.
For adequate and long lasting machine support, proper grout se-
lection and placement is essential. Carrier recommends that only
pre-mixed, epoxy type, non-shrinking grout be used for machine
installation. Follow manufacturer’s instructions in applying grout.
1. Check machine location prints for required grout thickness.
2. Carefully wax jacking screws for easy removal from grout.
3. Grout must extend above the base of the soleplate and there
must be no voids in grout beneath the plates.
4. Allow grout to set and harden, per manufacturer’s instruc-
tions, before starting machine.
5. Remove jacking screws from leveling pads after grout has
hardened.
Fig. 44 — Accessory Isolation
OUTSIDE EDGE OF
1'-3 7/8"
[403mm]
CONDENSER TUBESHEET.
OUTSIDE EDGE OF
(TYPICAL BOTH ENDS)
EVAPORATOR TUBESHEET.
(TYPICAL BOTH ENDS)
[997mm]
3'-3 1/4"
Y*
[387mm]
TYPICAL
1'-3 1/4"
14'-9"
[4496mm]
SUPPORT PLATE
X*
[4286mm]
14'-0 3/4"
[105mm]
X
TYPICAL
[13mm]
0'-0 1/2"
[213mm]
0'-8 3/8"
0'-4 1/8"
0'-9"
Y
TYPICAL
[229mm]
0'-3"
[76mm]
ACCESSORY SOLEPLATE
TYPICAL
0'-3 1/2"
[89mm]
[610mm]
2'-0"
[38mm]
0'-1 1/2"
TYPICAL
CL
EVAPORATOR & COMPRESSOR
REAR
FRONT
SUCTION END
DISCHARGE END
CL
CONDENSER
a23-1684
*See Fig. 43 or 44.
IMPORTANT: Chiller support plates must be level within
1/2 in. from one end to the other end of the heat exchang-
ers for effective oil reclaim system operation.
VIEW Y-Y
a23-46
NOTES:
1. Dimensions in ( ) are in millimeters.
2. Isolation package includes 4 shear flex pads.
/LEG
VIEW X-X
LEGEND
NOTES:
1. Dimensions in ( ) are in millimeters.
2. Accessory (Carrier supplied, field installed) soleplate package
includes 4 soleplates, 16 jacking screws and leveling pads.
3. Jacking screws to be removed after grout has set.
4. Thickness of grout will vary, depending on the amount neces-
sary to level chiller. Use only pre-mixed non-shrinking grout,
Ceilcote 748 OR Chemrex Embeco 636 Plus Grout 0
-1-1/2
(38.1) to 0
-2-1/4
(57) thick.
HRS —
Hot Rolled Steel
ACCESSORY SOLEPLATE DETAIL
a19-1110
Summary of Contents for AquaEdge 23XRV
Page 53: ...53 Fig 58 23XRV Controls Schematic ...
Page 54: ...54 Fig 58 23XRV Controls Schematic cont FROM 2000767952 SHEET 3 ...
Page 55: ...55 Fig 58 23XRV Controls Schematic cont ...
Page 56: ...56 Fig 59 23XRV Controls Schematic Rockwell Standard Tier VFD Shown ...
Page 57: ...57 Fig 60 23XRV LF2 VFD Wiring Diagram ...
Page 65: ...65 Fig 70 23XRV Insulation Area Units with P Compressor ...