background image

30

Controls Operation

Before proper control operation can be verified, all other systems

must be operating properly. The correct water and air temperatures

must be present for the control function being tested. Some con

-

trols and features are designed to not operate under certain condi

-

tions.  For  example,  on  a  two-pipe  cooling/heating  system  with

auxiliary electric heat, the electric heater cannot be energized with

hot water in the system. 

A wide range of controls, electrical options and accessories may

be used with the equipment covered in this manual. Consult the

approved unit submittals, order acknowledgments, and other liter

-

ature for detailed information regarding each individual unit and

its controls. Since controls and features may vary from one unit to

another, care should be taken to identify the controls used on each

unit and their proper control sequence. Information provided by

component  manufacturers  regarding  installation,  operation,  and

maintenance of their individual controls is available upon request. 

When changing from one mode to another (cooling to heating or

heating  to  cooling),  it  may  take  some  time  to  actually  notice  a

change in the leaving air temperature. In addition, some units may

be designed for a very low air temperature rise in heating. Before

declaring a unit inoperative or a component defective, it may be

necessary to verify operation by more than one method.

SERVICE

Each unit on a job will have its own unique operating environment

and conditions which may dictate a maintenance schedule that dif

-

fers from other units on a job. A formal schedule of regular main

-

tenance and an individual unit log should be established and main

-

tained. This will help to achieve the maximum performance and

service life of each unit on the job.

Excessive Condensation on Unit 

Running chilled water through a fan coil unit with the unit fan off

can cause excessive condensation. If fan cycling is used, a water

flow control valve should be installed to shut off the water when

the fan stops.

Other methods of control that avoid condensation problems are as

follows:

1. Continuous fan operation with motorized chilled water valve

controlled by a thermostat.

2. Continuous fan operation with thermostat control to switch

fan from high to low speed (instead of off).

To Clean Coil

Coils may be cleaned by removing the filter and brushing the en

-

tering air face between fins with a stiff brush. Care should be taken

to not damage coil fins. Brushing should be followed by cleaning

with a vacuum cleaner. If a compressed air source is available, the

coil may also be cleaned by blowing air through the coil fins from

the leaving air face. This should again be followed by vacuuming.

Units provided with the proper type of air filters, replaced regular

-

ly, will require less frequent coil cleaning.

Check Drain 

Lock open and tag unit electrical service switch.

Check drain pan, drain line and trap before initial start-up and at

start  of  each  cooling  season. A  standard  type  pipe  cleaner  for

3/4 in. ID (Inside Dimensions) pipe can be used to ensure that pipe

is clear of obstruction so that condensate is carried away. Check

the drain line at filter cleaning time during the cooling season. Be

sure that debris has not fallen into unit through supply-air grille.

Should the growth of algae and/or bacteria be a concern, consult

an air conditioning and refrigeration supply organization familiar

with local conditions for chemicals or other solutions available to

control these agents.

Fan Motor Bearings

Lock open and tag unit electrical service switch.

Standard motors are permanently sealed and lubricated. No lubri

-

cation is required unless special motors have been supplied or un

-

usual operating conditions exist.

Motor/Blower Assembly

The type of fan operation is determined by the control components

and their method of wiring. This may vary from unit to unit. Refer

to the wiring diagram that is attached to each unit for that unit’s in

-

dividual operating characteristics.

All motors have permanently lubricated bearings. No field lubri

-

cation is required.

Should the assembly require more extensive service, the motor/

blower assembly may be removed from the unit to facilitate such

operations as motor or blower wheel/housing replacement, etc.

Dirt and dust should not be allowed to accumulate on the blower

wheel or housing. This can result in an unbalanced blower wheel

condition which can damage a blower wheel or motor. The wheel

and housing may be cleaned periodically using a vacuum cleaner

and  a  brush  taking  care  not  to  dislodge  the  factory  balancing

weights on the blower wheel blades.

Clean Fan Wheel

Lock open and tag unit electrical service switch.

For access to fan assembly, remove front or bottom panel. Fan as

-

sembly may be removed from its tracks if unit has a long conduit

lead. Dirt and debris should not be allowed to accumulate on the

blower wheel or housing. This can result in an unbalanced blower

wheel condition which can damage a blower wheel or motor. The

wheel and housing may be cleaned periodically using a vacuum

cleaner and a brush, taking care not to dislodge the factory balanc

-

ing weights on the blower wheel blades.

Table 3 — Water Quality Parameters

a,b

NOTE(S):

a. Maximum water operating temperature: 190°F (98°C).

b. Maximum allowable water pressure: 500 psig (3447 kpa).

WATER CONTAINING

REQUIRED CONCENTRATION

Sulphate

Less than 200 ppm

pH

7.0 to 8.5

Chlorides

Less than 200 ppm

Nitrate

Less than 100 ppm

Iron

Less than 4.5 mg/l

Ammonia

Less than 2.0 mg/l

Manganese

Less than 0.1 mg/l

Dissolved Solids

Less than 1000 mg/l

CaCO

3

 Hardness

300 to 500 ppm

CaCO

3

 Alkalinity

300 to 500 ppm

Particulate Quantity

Less than 10 ppm

Particulate Size

800 micron max

IMPORTANT:  Information  regarding  safety  precautions  con

-

tained in the preface at the beginning of this manual should be

followed during any service and maintenance operations.

Summary of Contents for 42S Series

Page 1: ...STRUCTION 32 APPENDIX B POTENTIOMETER ADJUSTMENT 35 APPENDIX C CONTROL OPERATIONS 36 APPENDIX D EVO ECM 4 SPEED ADJUSTMENT 41 START UP CHECKLIST FOR 42S SERIES FAN COIL AIR CONDITIONERS CL 1 SAFETY CO...

Page 2: ...angement should be verified against the order documents Should any discrepancy be found the local sales representative should be notified immedi ately so that proper action may be taken Should any que...

Page 3: ...tural support Due to variations in building construction floor plans and unit configurations each installation is different The actual step by step method of installation may vary from unit to unit H...

Page 4: ...ox lb per row of coil 1 79 2 63 3 45 4 09 4 09 4 39 COILS FPI 14 fins inch BLOWER qty 42SGA SH SU SGM SGS SM 1 1 1 1 1 1 1 1 1 42SJ 2 2 2 2 2 2 FILTERS Nominal Size in 1 in thick 12 1 2 x 24 1 4 16 1...

Page 5: ...14 356 8 203 14 356 6 152 14 356 10 254 17 432 1 1 2 38 1 1 2 38 14 356 04 12 305 06 18 457 10 254 18 457 16 406 12 305 20 508 1 25 2 51 18 457 08 12 305 10 22 559 16 406 22 559 8 203 18 457 16 406 24...

Page 6: ...6 Fig 4 Riser Chase Unit Width Riser Chase Depth All model sizes 5 1 2 141 Unit Depth Riser Chase Risers Unit Height Stack Unit...

Page 7: ...E DIMENSIONS in mm SIDE FRONT SUPPLY DOUBLE SUPPLY TOP SUPPLY SINGLE DIMENSIONS A B A B C D E F G H 03 14 356 8 203 14 356 6 152 14 356 10 254 17 432 22 1 8 562 22 1 8 562 14 3 4 375 04 12 305 8 203 0...

Page 8: ...to permit expansion and contrac tion of risers Coil connections to be at the center of the slots 11 See unit arrangements for supply and return air orientation 12 Dimensions are in inches Dimensions...

Page 9: ...1 Service Switch Optional NOTES 1 Units are fabricated of galvanized steel with a 16 gauge galvanized fan deck 2 All risers are insulated 3 Thermostats shipped loose for field installation 4 Risers ar...

Page 10: ...to permit expansion and contrac tion of risers Coil connections to be at the center of the slots 8 See unit arrangements for supply and return air orientation 9 Dimensions are in inches Dimensions in...

Page 11: ...9 Return Air Opening 10 Drain Knockout s Side Panels 11 Access Panel Control Box 12 Riser Supply and Return 13 Riser Drain 14 Isolation Ball Valves 15 Strip Heater Optional E Heat 16 Heat Limit Switch...

Page 12: ...ES 1 Units are fabricated of galvanized steel with a 16 gauge galvanized fan deck 2 All risers are insulated 3 Thermostats shipped loose for field connection 4 Risers are factory piped to coil with va...

Page 13: ...and control box are insulated 7 Riser length floor to floor 2 in 51 mm Maximum riser length is 119 in 3023 mm 8 Maximum riser size is 2 1 2 in 64 mm diameter If larger sizes are required please consul...

Page 14: ...16 406 4 102 NOTES 1 Plenum box adds 22 in 559 mm to unit height adds 26 lb 11 8 kg to unit weight and is factory installed 2 1 4 in closed cell insulation is standard for the plenum box 3 Side suppl...

Page 15: ...ensions in inches PANEL NO UNIT SIZE A 1 42SG SJ SU 03 04 15 5 06 08 19 5 10 12 23 5 42SM 14 16 20 29 5 2 42SG SJ 03 04 15 5 06 08 19 5 10 12 23 5 3 42SG SJ 03 04 15 2 06 08 19 2 10 12 23 2 PANEL NO 1...

Page 16: ...TE S a Dimensions in inches PANEL NO UNIT UNIT SIZE A 4 42SG SJ SU 03 04 15 1 06 08 19 1 10 12 23 1 5 42SG SJ 03 04 15 1 06 08 19 1 10 12 23 1 6 42SG SJ 03 04 16 7 06 08 20 7 10 12 24 7 PANEL NO 4 54...

Page 17: ...should never be lifted up or pulled down to meet the riser on the floor below or above 4 Install isolator pads beneath the four corners of unit if appli cable 5 Before anchoring the equipment in place...

Page 18: ...unit frame d After all units in a stack are anchored make unit to unit riser joints First center each coil to riser line within the expansion slot in the unit back panel Each riser joint must be in ve...

Page 19: ...dary arrangements Potential Universal Arrangement Unit Configurations Risers Three Locations The pre installed supply return and drain risers 2 pipe or 4 pipe applications can be oriented on any of th...

Page 20: ...taller Riser to Unit Installation Before making the riser joints the riser insulation must be pulled back away from the joint and protected from heat during the braz ing process Each riser joint must...

Page 21: ...bottom of the unit as shown in Fig 26 10 Push the rubber drain hose over the riser drain stubout Be careful not to bend the drain stubout 11 Adjust the hose clamp over the riser stubout and rubber hos...

Page 22: ...nly All risers are factory fabricated and shipped loose for field installation It is important that you identify all of the unit feature locations before proceeding with the installation see Fig 11 Un...

Page 23: ...ical 3 The plastic flare caps on the end of the riser ball valves should be removed and discarded 4 All mega stack units use reinforced braided stainless steel flexible hose kits for piping between fi...

Page 24: ...to withstand the total operating pressure both static and pumping head to which the system will be subjected Low temperature lead alloy solders such as 50 50 and 60 40 are normally not suitable Chille...

Page 25: ...th optional auxiliary electric heat is desired an additional aquastat is required If the valve package is field supplied the aquastat must be installed in a location where it will sense the water temp...

Page 26: ...ing However drywall secured with adhesive bonding alone is NOT recommended CONCEALED UNIT ENCLOSURE Concealed units are designed to have gypsum board or other types of wall board applied directly to t...

Page 27: ...y steam of water begins to escape close valve Vent release air slowly usually dripping water into drain pan in the process Make sure all service valves are open and that the motorized control valves i...

Page 28: ...ize themselves with the unit options and accesso ries and control sequence to understand the proper system opera tion All personnel should have a good working knowledge of general start up procedures...

Page 29: ...hould not be attempted by unqualified personnel The system must be complete and all components must be in operating condition BEFORE beginning water system balancing operations Each hydronic system ha...

Page 30: ...nd tag unit electrical service switch Check drain pan drain line and trap before initial start up and at start of each cooling season A standard type pipe cleaner for 3 4 in ID Inside Dimensions pipe...

Page 31: ...be replaced on a regular basis The time interval be tween each replacement should be established based on regular in spection of the filter and should be recorded in the log for each unit Refer to the...

Page 32: ...OUT CONSTRUCTION SIZE TYPE OF INSTALLATION TYPE 1 TYPE 2 TYPE 3e e Not recommended for Siamese Ditto Installation W x L in W x L in W x L in Single Unit and Siamese Ditto 03 04 96 5 7 8 x 15 5 1 8 x...

Page 33: ...Table D Short 79 in Cabinet 4 Pipe 42S Units a b c d NOTE S a CLEAR HEIGHT is the dimension from the floor to ceiling See Fig A of this appendix b The above charts allow 1 in tolerance in clear height...

Page 34: ...o Floor Clear Height Riser Length Block out Length Unit Unit Block out Width NOTE Riser Length Floor to floor dimensions 2 in maximum riser length of 115 in When riser length must exceed 115 in use 10...

Page 35: ...outputs high medium and low 5 High Speed Close high speed relay by applying 24 v to the high terminal Using a small screwdriver turn the VR3 poten tiometer so the meter measures 4 51 vdc This will se...

Page 36: ...REMOTE SHUTDOWN INPUT 1 Provides dry contact for signal to BAS system I O a Dry Normally Open b Wet Normally Open c Discrete Coil 2 When contact activated a Motor OFF b Actuator OFF c Electric Heat O...

Page 37: ...Fan Low Speed W1 HTG Heat Y1 CLG Cool W2 HT2 Heat Stage 2 Y2 CL2 Cool Stage 2 R 24V 24V Controller Power COS Changeover Sensor RAS Room Air Sensor Table F 0 10 Variable Airflow ECM CONNNECTION FUNCTIO...

Page 38: ...adjusted from 0 to 100 of the motor s factory programmed operating range Use voltmeter and airflow chart on control box cover to set values Adjusting the potentiometers requires the use of a Multi met...

Page 39: ...ll actuate and supply 24VAC to Pin 12 of connector CN5 When 0 10VDC is applied to HTG that control signal will passively be present at Pin 8 of the CN6 connector HTG LED shows GREEN Signal for 1st sta...

Page 40: ...40 APPENDIX C CONTROLS OPERATION CONT Fig H Typical Wiring Diagram NOTE Wiring diagram also available through QR code found on the unit serialized name plate label...

Page 41: ...lead of the meter to the high speed Flo1 terminal below the potentiometer 6 High Speed Using a small screwdriver turn the Flo1 potenti ometer so the meter measures 4 51 vdc This will set the ECM speed...

Page 42: ...s the right to discontinue or change at any time specifications or designs without notice and without incurring obligations Catalog No 04 53420024 01 Printed in U S A Form 42S 5SI Pg 42 9 22 Replaces...

Page 43: ...l supply voltage 8 Proper access provided for unit and accessories 37 Record ambient temperatures 9 Proper electrical service provided 38 Check all wiring for secure connections 10 Proper overcurrent...

Page 44: ...______________________________________________________ _________________________________________________________________________________________________________________________________________________...

Reviews: