1 - PRECAUTIONS

1.1 - Operating limits

1.1.1 - Cooling mode

Minimum supply air temperature 12°C when the unit is installed 

where the ambient temperature is 27°C dry bulb with 65% relative 

humidity.

1.1.2 - Heating mode

Max.  supply  air  temperature  =  60°C  to  avoid  damage  of  the 

discharge  spigots.  To  avoid  all  risks  of  stratification,  Carrier 

recommends to keep the supply air temperature below 35°C.

1.1.3 - Operating environment

The 42BJ ICM LEC has been designed for indoor application in 

‘urban’  conditions  having  a  non-corrosive,  dust-free  and  non-

marine environment.
The  concentrations  of  the  following  chemicals  must  not  be 

exceeded in any event:

 

-

SO

2

  

<   0,02 ppm

 

-

H2S  

<   0,02 ppm

 

-

NO, NO

2

   <   1 ppm

 

-

NH

3

  

<   6 ppm

 

-

N

2

O  

<   0,25 ppm

Do not install a unit where flammable gases or products of an 

acidic or alkaline character may be present. The copper/aluminium 

coil or components inside the unit could suffer irreparable corrosion 

damage in their presence.

1.1.4 - Recommended coil water quality

At  installation  handover,  and  then  periodically  every  year,  it  is 

advised  to  analyse  the  water  for  bacteria  (detection  of  ferro-

bacteria,  H2S-producing  and  sulphate-reducing  bacteria)  and 

chemicals  (in  order  to  avoid  problems  due  to  corrosion  and 

scaling).

The water circuit must include all the necessary elements for the 

treatment of the water: filters, additives, intermediate exchangers, 

purges, drains, isolating valves, etc., according to the analysis 

results.
The results must be in accordance with the values shown below:

 

-

Total hardness in mmol/l:   1   < mmol/l  

< 1,5

 

-

Chloride [CL

-

]  

  < 10 mg/litre

 

-

Sulphate [SO

4

2-

]  

  < 30 mg/litre

 

-

Nitrate [NO

3

-

]  

  = 0 mg/litre

 

-

Dissolved iron:  

  < 0,5 mg/litre

 

-

Dissolved oxygen:  

4   < [O

2

] < 9 mg/litre

 

-

Carbon dioxide [CO

2

]  

  < 30 mg/litre

 

-

Resistivity:  

20 Ohm·m   < Resistivity < 50 Ohm·m

 

-

pH:  

6,9  < pH < 8

1.2 - Clearances required

Please refer to Fig. 1.

1.3 - Receiving a shipment - installation 

methods

When receiving a shipment, check the condition of the goods and 

report  any  damage  in  transit  to  the  shipping  company.  Do  not 

unpack the units until just before they are due to be installed, and 

make sure they are as close as possible to the installation site 

when unpacking them. Do not place heavy articles of any sort on 

them.

1.4 - Supply voltage 230V ± 10% - 50 Hz

Check that the supply voltage and frequency correspond to the 

values of the unit to be installed.

WARNING: Failure to take proper account of the above advice 

and unauthorised modification of the electrical connections 

will render the Carrier warranty on the product null and void.

8

Summary of Contents for 42BJ ULTRA

Page 1: ...I N S TA L L AT I O N I N S T R U C T I O N S Original document INDIVIDUAL COMFORT MODULE FOR VARIABLE AIR VOLUME SYSTEMS 42BJ MCI LEC Sizes 1 9 2 9 4 9 ...

Page 2: ...2 ...

Page 3: ...n conditions 9 2 4 Caution for the control of the 42BJ ICM LEC 9 2 5 Regulations 9 3 INSTALLATION OF THE UNIT 10 3 1 Installing the unit in the false ceiling 10 3 2 Installation procedure 10 3 3 Remocal procedure 10 4 COMPONENTS 11 4 1 Fan motor assembly 11 4 2 Water coil 11 4 3 Duct connection spigots 11 4 4 Optional air filter and filter access air filter replacement 11 4 5 Constant volume fresh...

Page 4: ...B C D E F G H I 4 ...

Page 5: ...m m 50 mm l s m3 h A B MR60 17 60 4 4 4 4 MR75 21 75 4 3 4 3 MR85 24 85 3 3 3 2 MR90 25 90 3 2 2 2 MR100 28 100 2 1 2 1 MR105 29 105 2 1 1 1 MR110 31 110 1 1 1 1 MR120 33 120 3 3 MR130 36 130 2 1 MR140 39 140 1 1 MR160 44 160 L M N O 5 ...

Page 6: ... A 2 wV In Out In Out Cold Hot Ø 16 61 75 75 10 5 4 Ø 1 2 gas 25 82 5 69 188 A 3 wV In 42BJ A 1 9 151 mm 2 9 190 mm 42BJ MCI LEC 4 9 Out Ø 16 75 61 4 Ø 1 2 gas 163 5 192 225 69 2 wV In In Out Cold Hot Out Ø 16 75 61 4 Ø 1 2 gas 163 5 192 62 5 69 3 wV In In Out Cold Hot 6 ...

Page 7: ...g device for installation in a false ceiling H I Levelling the unit J Condensate drain pipe K Several units connected to one condensate collector L Fresh air controller modification M Fan motor assembly removal 12a Door 12b Locking screw 12C Fan fixing screw N Electric heater removal O Underfloor installation P Coil water inlet outlet positions sizes 1 9 and 4 9 In Water in Out Water out Hot Hot w...

Page 8: ...acteria and chemicals in order to avoid problems due to corrosion and scaling The water circuit must include all the necessary elements for the treatment of the water filters additives intermediate exchangers purges drains isolating valves etc according to the analysis results The results must be in accordance with the values shown below Total hardness in mmol l 1 mmol l 1 5 Chloride CL 10 mg litre...

Page 9: ...rown green yellow and its cross section and type must comply with the specifications set out by the applicable EN or IEC standard Refer to the selection sheet or the name plate to determine the maximum input current These devices are not supplied by Carrier In general terms the following rules must be applied Upstream over voltage protection Unit without electric heater T2A Unit with electric heat...

Page 10: ... over the whole horizontal pipe run Install a 50 mm minimum siphon to prevent gases and odours from flowing back into the ceiling void If several units are connected to a common collector a device must be installed Fig 10 Before operating the unit ensure that the water flows into the internal condensate drain pan by pouring some water into it If problems are detected check the drain pipe slope and l...

Page 11: ...d all air from the coil during refilling ATTENTION It is advisable to tighten the valve body to the coils with caution 15 N m is sufficient to ensure they are not damaged 4 2 2 Coil inlet outlet positions Fig 15 Water inlets outlets sizes 1 9 2 9 Water inlets outlets size 4 9 ATTENTION Carefully observe the direction indicated by the arrow on the valves based on the connection side and the valve typ...

Page 12: ...e actuators must be connected to the power supply to open the valves via a command from the wall thermostats or from the BMS 4 6 2 Actuator replacement procedure The actuators on both the chilled water and the hot water valves may be replaced if either develops a fault Disconnect the power supply to the unit before carrying out any work on a unit Disconnect the actuator power supply cable equipped...

Page 13: ...umeric controller 4 10 Adjustable feet accessories for installation in a false floor void 4 10 1 Introduction An ICM may be installed in a floor void Adjustable feet with built in vibration absorbers are available as accessories for installation on site For further information please contact your local Carrier representative 4 10 2 Procedure for fitting see Figs 14 and 15 a Install angle bracket 1 u...

Page 14: ... high pressure PTC 4 wired stages Digit 14 F F5 access from below G F5 side access H F5 access from above K F6 access from below L F6 side access M F6 access from above S Activated carbon filters UVPCO access from below T Activated carbon filters UVPCO side access U Activated carbon filters UVPCO access from above Digit 15 None A 125 mm Ø fresh air spigot only B 8 3 l s 30 m3 h C 16 6 44 4 l s 21 ...

Page 15: ...15 ...

Page 16: ...7 2021 replaces No 14281 11 2011 The manufacturer reserves the right to modify the product specifications without prior notice Manufacturer Carrier S C S Rte de Thil 01120 Montluel France Printed in the European Union ...

Reviews: