INSTALLATION GUIDE
canusacps.com
Flame Intensity &
Torch Size
Epoxy Primer
Pre-Heat
Surface Preparation
Epoxy Primer Application
Sleeve Installation
GTS-80/T
4
8
12
Ensure that the mainline coating edges
are beveled to 30°. If there is the pres-
ence of oil, grease, or other surface
contaminants; clean the exposed steel
and adjacent pipe coating with a solvent
cleanser.
Apply mixed epoxy to a minimum uni-
form thickness of 4 mils on all exposed
bare metal plus 10 mm (0.5”) onto the
adjacent pipe coating.
Centre the sleeve over the joint so that
the sleeve overlaps between the 10 and
2 o’clock positions. Press the underlap
fi rmly into place. Remove the remaining
release liner.
7
11
Follow the Preparation, Mixing and
Application instructions provided with
the supplied Canusa Epoxy Pack. For
bulk quantities: mix the primer cure with
the primer base (4 parts base to 1 part
cure by volume). Stir for a minimum of 30
seconds to assure uniform mixture.
Partially remove the release liner and
gently heat the underlap approximately
150 mm (6”) from the edge.
Global Transmission Sleeve
Canusa torch, propane tank, hose &
regulator; Canusa E-Primer, thickness
gauge Mixing sticks, cups & applicator
pads; Digital Thermometer with suit-
able probe, fl at roller; Appropriate tools
for abrasion (rasp, fi le, or sandpaper);
Standard safety equipment (gloves, gog-
gles, hard hat, etc.)
Wipe clean or air blast the steel and
coated areas to remove foreign materials.
Ensure that the epoxy primer is dry to
the touch prior to sleeve installation.
Equipment List
2
6
10
1
5
9
GTS-80 Global Transmission Sleeves are
shipped pre-cut with a pre-attached clo-
sure. Bulk quantities are also available.
The adhesive is protected from contami-
nation by an inner liner.
Warm the joint area to 40-50°C (100-
120°F) before grit blasting. Thoroughly
clean the weld area with a sand or grit
blaster to “near white metal” SIS Sa
2½ or equivalent. Abrade the mainline
coating adjacent to the weld area to a
distance 50 mm (2”) beyond the sleeve
width.
Preheat the epoxy to a temperature of
110°C and the abraded mainline coat-
ing to be covered by the sleeve to a
minimum of 100°C with the appropriate
propane torch, induction heating or infra-
red heating equipment.
Do not use an
intense fl ame on the mainline coating.
If
a fi lm develops on the mainline coating
because of preheat, use a surface abra-
sion tool to remove it.
Product Description
Pipe O.D.
≤ 450mm
(18”)
Minimum Torch Size:
150,000 BTU/hr.
Minimum Torch Size:
300,000 BTU/hr.
Use
moderate to high
fl ame intensity for pre-
heating and shrinking.
Use
moderate
fl ame intensity for pre-
heating and shrinking.
Pipe O.D.
> 450mm
(18”)
3
Mainline Coating
100°C (212°F)
110°C (230°F)
g
)
)
SIS Sa 2½
SSPC SP 10
Slee
ve
Width
50 mm + Slee
ve
+ 50 mm
Cure
Base
Base
Epoxy CB
Epoxy BP
Cure
Epoxy
Cure
Base