CANNON Instrument Company® | Getting Started
13
5.
Slowly pour a small amount of silicone fluid into the bath. Check for leaks. Continue filling until the
bath fluid reaches the cold fill level (marked with a thin black/red line on the glass), approximately
0.9 L.
6.
Repeat steps 3 through 5 for the second bath.
Connect Cables
1.
Connect the MAINS AC power cord to the CAV 4.2.
2.
Plug the power cord into the MAINS AC outlet at the work station.
3.
(optional) Connect the CAV 4.2 to the network switch with one CAT cable.
4.
(optional) Connect the network switch to the PC with a CAT cable and USB adapter.
Set Bath Temperature (
CAV 4.2 GUI
)
Set the temperature of the baths before calibrating the instrument.
1.
From the main screen, see Figure 7, click the target temperature button
for the appropriate
bath. The temperature settings screen opens.
Figure 7 — Main Screen
Target
temperature
Current
temperature
Target
temperature
Current
temperature