FIGURE 7-14. UTDK duckbill guy anchor being driven into the ground
2. Attach a high-lift jack to the loop and jack the anchor up about 6 inches to rotate the
anchor into the load-lock position (
(p. 23)).
WARNING:
Failure to install and lock the anchor at the correct angle will result in the anchor cable
cutting through the soil until the angles equalize, causing slack in the guy wires.
FIGURE 7-15. UTDUK duckbill in load-lock position