Fireplace Concrete Pad Construction:
Call 811 for information on underground utility marking. Select desired location and excavate 52” L x
65 3/4” W x 12 3/4” D area for concrete pad. Fill excavated area with approximately 6” of ¾” clean
gravel, compacting every 3”. Frame remaining 4” with 2” x 4” lumber to create a level pad. (Be sure 2”
x 4” wood frame is perfectly level, front to back and side to side) See attached drawing for details of
steel reinforcement rod placement. Fill 2” x 4” wood frame with a 4,000 psi strong concrete mix.
*Allow pad to cure for minimum of 48 hours.
*Note: (Wood Box Additions) If you are going to add fire wood box extensions, either a single unit or a
set, it will be necessary to construct an additional concrete pad for each unit added.
Construccion concreta del cojín de la chimenea:
Llamada 811 para la información sobre la marca para uso general subterráneo. Seleccione deseó la local
-ización y excavan 52” L x 65 3/4” W x 12 3/4” D áreas para el cojín concreto. Instale cuatro 8” tubos
concretos del diámetro a la helada-línea según código local. Llene el área excavada de aproximada-
mente 6” de ¾” grava limpia, compactando cada 3”. Capítulo 4” restantes con madera de construcción
de 2” x 4” para crear un cojín nivel. (Sea sure el marco de madera 2” x 4” es perfectamente nivel, frente
ha atrás y lado a lado) vea el dibujo atado para los detalles de la colocación de acero de la barra del re-
fuerzo. Llene el marco de madera de los tubos concretos y de 2” x 4” de una mezcla de hormigón fuerte
de 4,000 PSI.
*Permita que el cojín cure para el mínimo de 48 horas.
*Note: (Adiciones para la caja de lena) Si usted va a agregar las extensiones de madera de la caja del
fuego, una sola unidad o un sistema será necesario construir los cojines concretos adicionales para cada
unidad agregada.