In compliance with the current norms, the machine should be installed only by a technical person qualified for this type 
of work. During installation, ensure that: 

 

 

- The machine is moved as given in chapter II.1. 

 

 

- The required personal protection devices are worn so as to avoid injuries caused by electrical and mechanical 

hazards (injuries by touching panels, sharp edges, etc.) 

 

 

- Electrical connections are made after the power supply has been shut off, in compliance with the recommen-

dations given in chapter III. 

 

 

- Grounding is carried out in compliance with current standards. 

 

 

- The machine is powered on when installation has finished (ducting installed and inspection doors closed).

 

 

 

 

 

 

I / RECEIVING THE EQUIPMENT 

 

 

Diablo are delivered on stringers or palettes then wrapped in plastic film.. 

 

I.1 / Receipt of the goods

 

 

When the equipment is received, the state of the packaging and the equipment must be checked. In the event of 

damage, make an accurate note of any problems on the carrier's delivery note.

 

 

I.2 / Unpacking 

 

When the equipment is unpacked, check the following:

 

- The total number of packages are present.

 

- All accessories are present (dampers, roof, electric switchgear, etc.). After unpacking the equipment, the waste must 
be disposed of in compliance with the current standards. No packaging should be discarded into the environment 

 

I.3 / Storing 

 

The equipment must be stored in shade, in a dry place, at a temperature between -20°C and 40°C. 

II / INSTALLATION 

 

 

II.1 / Handling 

 

The units must only be moved in their installation position.

 

 

If the device is handled using a fork-lift truck, ensure this supports the load-bearing structure and does not touch 

the panels enclosing the unit.

 

 

If the device is moved using a crane, use four cables of identical lengths. These must be at least as long as the 

greatest distance between two fastening points.

 

 

If L + W + H > 5m 

⇒ 

⇒ 

⇒ 

⇒ 

then the case must be lifted using a lifting beam.

 

 

II.2 / Space required 

 

Generally speaking, it is desirable to provide access space of at least the width of the unit on the access side for 

maintenance. 

 

 

II.3 / Installation 

 

The unit must be laid on a sufficiently rigid and flat surface (use vibration mounts if necessary). For the DIABLO 

connection, select duct sections based on dimensions of the flexible bands that should be properly stretched.

 

Install the unit such that bad weather or ambient temperature cannot damage the internal items of the unit during instal-
lation as well as when used later (possibly provide a protective cap).

 

 

Summary of Contents for Diablo F400-120

Page 1: ...DIABLO DIABLO TWIN F400 120 SMOKE AND HEAT EXHAUST FAN OPERATING AND COMMISSIONING MANUAL 2015 03 1 ...

Page 2: ...All accessories are present dampers roof electric switchgear etc After unpacking the equipment the waste must be disposed of in compliance with the current standards No packaging should be discarded into the environment I 3 Storing The equipment must be stored in shade in a dry place at a temperature between 20 C and 40 C II INSTALLATION II 1 Handling The units must only be moved in their installa...

Page 3: ...ries BEFORE SWITCHING ON THE DIABLO PAY ATTENTION THAT ALL THE SCREWS ARE WELL TIGHTENED IN PARTICULAR THE ROTATING COMPONENTS III ELECTRIC WIRING OF THE 3 PHASE MOTOR Electric connection will be done on the padlockable switch or on the optionnal control box mounted on the DIABLO DIABLO TWIN In this case refer to the manual with control box 1 Speed 2 tensions Star Delta connexions 230V 400V 4 6 8 ...

Page 4: ... 1 tension Separated coils 400V 4 6 et 6 8 poles Safety switch III 2 2 speeds motor Dahlander III 3 2 Speeds motor Separated coils High speed Low speed 2 4 6 1 3 5 2 4 6 1 3 5 L1 L2 L3 2 4 6 1 3 5 2 4 6 1 3 5 L1 L2 L3 2U 2V 2W 1U 1V 1W 2U 2V 2W 1U 1V 1W 2 4 6 1 3 5 2 4 6 1 3 5 L1 L2 L3 2 4 6 1 3 5 2 4 6 1 3 5 L1 L2 L3 2U1 2V1 2W1 1U1 1V1 1W1 2U1 2V1 2W1 1U1 1V1 1W1 ...

Page 5: ...r which must be the same as written on the mo tor plate In case of overcurrent stop the unit and contacte your retailer IV 2 Fan When wiring is finished check the direction of rotation of the fan reverse 2 of the phases on the motor to invert the direction of rotation NOTA a fan that does not rotate in the right sens do not have an apposite airflow but an airflow lower than forecasted An extended ...

Page 6: ...llation or on the motor support in standard This configuration has F400 120 certification When only using in variable comfort electric connection without logic 400 120 control box speed variation can be done with VFT or VFM frequency convertor When using in variable comfort and smoke exhaust electric connection with a logic 400 120 control box speed variation can only be done with VFT or VFM frequ...

Page 7: ...he fan box Check the ducts VI 2 Fans Dust the wheel if necessary Fill in the service manual below everytime an intervention is done on DIABLO DIABLO TWIN box Before to start any intervention you must electrically insulate the box with padlockable switch IPC on OFF position Date intervention Comments ...

Page 8: ...in the turbine Anti vibration moutings or fan chassis is broken Wrong direction of motor rotation Clean the wheel Replace anti vibration mountings Reverse 2 phases on motor Wrong airflow Wrong direction of motor rotation Wrong estimation of pressure drop in the duct network Reverse 2 phases on motor Modify duct network or contact us DIABLO DIABLO TWIN F400 120 SMOKE AND HEAT EXHAUST FAN 2015 03 Pa...

Reviews: