Commissioning | 7
Instruction Manual R5 RA 0165-0305 D_EN_en
23 | 44
7
Commissioning
NOTICE
The machine can be shipped without oil.
Operation without oil will ruin the machine in short time!
●
Prior to commissioning, the machine must be filled with oil, see
CAUTION
During operation the surface of the machine may reach temperatures of more than 70°C.
Risk of burns!
●
Avoid contact with the machine during and directly after operation.
CAUTION
Noise of running machine.
Risk of damage to hearing!
If persons are present in the vicinity of a non noise insulated machine over extended periods:
●
Make sure that ear protection is being used.
●
Make sure that the installation conditions (see
10]) are met.
Version with water-oil heat exchanger:
●
Turn on the water supply.
●
If the cooling water inlet is equipped with a water bypass valve (WBV), open it for approx. 90
seconds before the first machine start-up.
●
Make sure that cooling water requirements are fully complied with, see
●
Switch on the machine.
●
Make sure that the maximum permissible number of starts does not exceed 30 starts per hour.
Those starts should be spread within the hour.
●
Make sure that the operating conditions comply with the
38].
●
After a few minutes of operation, check the oil level and top up if necessary.
As soon as the machine is operated under normal operating conditions:
●
Measure the motor current and record it as reference for future maintenance and
troubleshooting work.
7.1
Conveying Condensable Vapors
Water vapor within the gas flow is tolerated within certain limits. The conveyance of other vapors
shall be agreed upon with Busch.
If condensable vapors are to be conveyed:
START
●
Close the isolation valve* and open the gas ballast valve** (GB)
●
Warm up the machine