To start an idle boiler after wet lay-up, use the
following procedure:
1.
the boiler was pressurized with
nitrogen, disconnect the nitrogen supply
source and vent the boiler.2. Using the
lowdown valve, drain the boiler
partially and make up with feedwater so
as to dilute the chemical residuals to
operating concentration levels.
3.
After the boiler water concentrations
and the water level are returned to
proper operating conditions, the boiler
can be started in the normal manner.
After Dry Lay-Up
To start an idle boiler after dry lay-up, use the
following procedure:
1. Disconnect the nitrogen supply source
and vent the boiler in a safe manner -
external to the building and away from
air intakes. Then thoroughly purge the
boiler of nitrogen with dry air.
2. The boiler was to have been cleaned
before the lay up procedure. So it is
necessary only to fill the boiler with
properly treated water. Then proceed
with start-up
N
OTE
:
OPERATING BOILERS MUST
BE REMOVED FROM SERVICE TO MINIMIZE
ADHERENCE OF BOILER WATER SUSPENDED
SOLIDS ON BOILER METAL SURFACES
.
R
EFER TO PREVIOUS INSTRUCTIONS FOR
BOILER WASHDOWN
.
C
AUTION
:
T
HE USE OF NITROGEN FOR
BLANKETING IS RECOMMENDED IN BOTH THE
WET AND DRY LAY
-
UP PROCEDURES
. E
VEN
THOUGH NITROGEN IN DILUTE QUANTITIES IN
NON
-
TOXIC
,
IT WILL NOT SUPPORT LIFE
.
P
RECAUTIONS MUST BE TAKEN BEFORE
ENTERING EQUIPMENT FILLED WITH
NITROGEN FOR INSPECTION OR ANY OTHER
PURPOSES
. T
HESE PRECAUTIONS SHALL BE AS
FOLLOWS
:
?
D
ISCONNECTION OF NITROGEN SUPPLY
LINE
?
C
OMPLETE PURGING AND VENTING OF
THE EQUIPMENT WITH FRESH AIR
?
T
ESTING OXYGEN LEVELS INSIDE
BEFORE ANY ATTEMPT TO ENTER
?
A
LL CONFINED ENTRY GUIDELINES
APPLICABLE TO SITE MUST BE FOLLOWED
A
PPROPRIATE CAUTION SIGNS SHALL BE
POSTED AROUND THE EQUIPMENT TO ALERT
PERSONAL THAT NITROGEN BLANKETING IS IN
USE
. A
BOILER LAID UP DRY MUST BE TAGGED
WITH INFORMATION THAT THE UNIT IS NOT TO
BE OPERATED UNTIL THE BOILER IS PROPERLY
REFILLED
.