Bryan Boilers A-H-FS-15-12-50-D operati Installation And Operating Service Manual Download Page 14

B O I L E R   F E E D   S Y S T E M  

D A T E :   4 / 3 / 0 3  

R E P : 2 / 1 / 9 9  

 

10

6. 

Considerations of warranty should the boiler system be used for temporary heat 
without adherence to the recommended start-up and operating procedures outlined in 
the instruction manuals. 

3.2 CLEANING THE BOILER AND SYSTEM – NEW SYSTEMS 

BOIL OUT PROCEDURE

The internal surfaces of a newly installed boiler will have oil, grease, or other protective coatings 
used in manufacturing.  Such coatings must be removed since these coatings lower the heat 
transfer rate and reduce operating efficiency.  The operator must be familiar with the procedure 
outlined in the boiler/burner operating instruction manuals. 

In combination with system contamination, bacteria may cause objectionable odors, sometimes 
resembling natural gas.  It is important to keep these fumes from air intake that would distribute 
them throughout the building.  On steam humidification systems this is especially critical.  Consult 
your local water treatment chemist for further information.  Your water consultant or water 
treatment company will be able to recommend a cleaning or boil out procedure. 

3.3 SYSTEM CLEAN OUT

 

Many boilers have been ruined with system contaminants such as pipe dope, cutting oil, metal 
shavings or chips, and other debris that are left in the piping.   

SYSTEM CLEANING PROCEDURE

For steam systems, the boiler will need to be connected to the header utilizing steam to purge the 
piping and thus push the debris out of the system.  However, at this time, all condensate must be 
wasted until it runs clear and water analysis of the condensate indicates that it is free of 
contaminants.  Steam trap strainers must be periodically opened and cleaned of any debris that 
accumulates. 

During this system clean out, the boiler make-up water must be properly softened and treated.  At 
the conclusion of the system clean out, the condensate must be reconnected. 

For existing steam systems, the installation process may have jarred debris loose.  Following the 
boil out of the new boiler, the condensate should be wasted until it is within proper guidelines.  
Check all steam trap strainers to assure their cleanliness.   

3.4 REPLACEMENT BOILER INSTALLATIONS: PROTECTION 
AGAINST CORROSION & SEDIMENT

 

CLEAN OR REPLACE ALL SYSTEM PIPING AND HEATING UNITS 

Arrange for chemical or mechanical cleaning of the entire system. A chemical treatment company 
should be consulted for the proper means of any chemical cleaning. 

Replace any piping considered to be deteriorated beyond safe or cleanable condition. 

Flush the system clean, being certain to isolate the boiler. 

DO NOT FLUSH THE SYSTEM THROUGH THE BOILER. 

Summary of Contents for A-H-FS-15-12-50-D operati

Page 1: ...Form 2143 Date 4 3 03 Repl 2 1 99 BRYAN STEAM LLC Installation and Operating Service Manual BOILER FEED SYSTEM 0 ...

Page 2: ...O N A N D O P E R A T I O N S E R V I C E M A N U A L BOILER FEED SYSTEM Bryan Steam LLC 783 North Chili Avenue Peru IN 46970 Phone 765 473 6651 Fax 765 473 3074 E mail bryanboilers iquest net Internet www bryanboilers com ...

Page 3: ...NO LINING A APEXIOR LINING B GALVANIZED LINING H TANK POSITION H HORIZONTAL TANK POSITION V VERTICAL TANK POSITION C COMPACT FS FEED SYSTEM TS TRANSFER SYSTEM 15 BOILER RELIEF VALVE SETTING 12 MAX BOILER HP 50 TANK SIZE GALLONS D NO OF PUMPS S SIMPLEX PUMPS D DUPLEX 2 PUMPS T TRIPLEX 3 PUMPS Q QUADRAPLEX 4 PUMPS ...

Page 4: ...PERATION 5 S E C T I O N 2 S T A R T U P 2 1 LIMIT TEST 6 7 2 2 OPERATING INSTRUCTIONS 8 2 3 MAINTENANCE SCHEDULE 8 S E C T I O N 3 S H U T D O W N A N D R E S T A R T 3 1 REQUIRED PRECAUTIONS DURING TEMPORARY USE 9 10 3 2 CLEANING THE BOILER AND SYSTEM NEW SYSTEMS 10 3 3 SYSTEM CLEAN OUT 10 3 4 REPLACEMENT BOILER SYSTEM INSTALLATION PROTECTION AGAINST CORROSION SEDIMENT 10 11 3 5 BOILER WATER TRE...

Page 5: ...the unit is not level or the floor is not in good condition a concrete foundation should be built the dimensions being larger than the outside dimensions of the boiler feed system base 1 2 CLEARANCES NOTE Adhere to all applicable local codes and NEC regarding system feed system installation and clearances The unit may need room for service accessibility and clearances for piping and electrical con...

Page 6: ...oming back should be of low pressure and will be introduced to atmospheric conditions once entering the tank If high pressure returns are required to return to this tank they should be reduced to a low pressure before entrance A steam pre heater assembly optional may have been supplied with the unit This connection is for high pressure steam and is reduced and controlled via a pressure temperature...

Page 7: ...le CFS The pump is a tank mounted pump mounted directly on the top of the tank The pump wetted parts are submerged in the tank with suction no less than 2 from the bottom of the tank The pump suction has a screen to protect the pump from debris This screen will need cleaned periodically for proper pump operation A throttling valve may be required in the pump discharge piping to keep the pump on it...

Page 8: ... temperature of 200 degrees F Some pumps may need by pass piping or a throttling valve in the discharge line to keep the pump flow at a satisfactory level on the pump curve All pump motors supplied are multi tapped Therefore before supplying power to the pumps make sure the motor is wired for the voltage being supplied 1 5 4 S T E A M P R E H E A T E R A S S E M B L Y O P T A steam pre heater asse...

Page 9: ...erature regulating valve should also be checked for obstructions 1 6 2 L E A K T E S T O F F E E D S Y S T E M A N D P I P I N G After completing the feed system installation the piping connections fittings attachments and adjacent piping must be inspected for leaks by filling the unit with water Inspect all openings and fittings for leaks removing any obstructions if necessary for proper evaluati...

Page 10: ...connects to the feed system and any other equipment or systems electrically interlocked with the unit All cover plates enclosures and guards must be in place at all times except during maintenance and servicing Close all valves to stop any water or steam from entering the feed system during maintenance or servicing OPTIONAL CONTROLS MAY HAVE BEEN SUPPLIED WITH THIS UNIT THAT ARE NOT ADDRESSED IN T...

Page 11: ...er level Please reference the wiring diagram supplied with the manual for proper wiring This connection should be checked before putting the boiler into operation making sure that it is operating correctly 2 1 5 B O I L E R F E E D P U M P The start up procedures found in the boiler feed pump manufacturer s data should be followed very carefully and may include venting the pump before actual opera...

Page 12: ...need to be open to the feed system in order to operate the feed system The tank should fill up to half full with make up water and the valves to the pumps on the suction end discharge side should also be opened and the strainers should be clean The pump should have been vented if required and all other instructions followed in this manual and also in the manufacturer s data manuals for each partic...

Page 13: ...lowing should be observed so as to assure the longevity of the feed system 3 1 2 O P E R A T O R S K I L L S R E S P O N S I B I L I T I E S During the temporary use period a single person must be assigned responsibility for the care and operation of the boiler feed system This person s responsibility must include but not be limited to the following 1 Knowledge of boiler system operation 2 Possess...

Page 14: ...pipe dope cutting oil metal shavings or chips and other debris that are left in the piping SYSTEM CLEANING PROCEDURE For steam systems the boiler will need to be connected to the header utilizing steam to purge the piping and thus push the debris out of the system However at this time all condensate must be wasted until it runs clear and water analysis of the condensate indicates that it is free o...

Page 15: ... that may be in the water supply A qualified water treatment chemist should be consulted and the water systematically treated OBJECTIVES The basic objectives of water treatment are Prevent the accumulation of scale and deposits in the boiler system Protect the boiler against corrosion Maintain the highest possible boiler efficiency Decrease the amount of boiler system down time from cleaning CONTI...

Page 16: ...no obstructions Check all limit controls as specified in manufacturer s manual Check float low water cutoff as described above Make sure all fuses are in operating order MONTHLY Make visual inspection of all wiring and components Confirm proper pump operation Check pump strainers for cleanliness ANNUALLY Check operating control and other electrical components for proper operating procedures as spe...

Page 17: ...uired as noted in this section to remove preservatives oil and grease LAY UP CONSIDERATIONS There are two basic methods of steam boiler lay up Wet lay up and Dry lay up The method used depends on The possibility that the boiler may need to be placed in operation on short notice Disposal of lay up solutions Freezing potential Wet Lay up is recommended for relatively short outages such as seasonal l...