REFRESH
INSTALLATION, OPERATION AND MAINTENANCE MANUAL
Assembly, Installation and Commissioning
2.
Assembly, Installation and Commissioning
2.1
Introduction
This section refers to all Refresh units.
2.1.1
Risk Assessment
A full
risk assessment
must be carried out before assembly and installation work commences on
site. The risk assessment should identify all Personal Protective Equipment (PPE) requirements.
This should be undertaken prior to the installation team arriving. Consideration should also be
given to drafting a full method statement for the process.
2.1.2
Access and Offloading
A safe
access
route must be established into the area in which the Refresh Unit will be installed.
This area is to be free from obstruction
A suitable
offloading
point must be identified before you begin to unload and it should be as close
to the installation area as possible
2.1.3
Warnings and Cautions
WARNING:
DO NOT INSTALL THIS EQUIPMENT FOR THE VENTILATION OF GAS, OIL OR SOLID
FUELLED EQUIPMENT. RISK TO THE HEALTH OF OPERATIVES CAUSED BY THE ACTUAL
COMBUSTION PROCESS WHICH USES UP AVAILABLE OXYGEN FROM THE COOKING
SPACE AND CREATES TOXIC CARBON BASED GAS EMISSIONS. ONLY ELECTRICALLY
POWERED EQUIPMENT MUST EVER BE VENTILATED BY THIS TYPE OF SYSTEM
WARNING:
COMPETANT PERSONNEL FAMILIAR WITH THE ASSESSMENT OF HAZARDS AND RISKS
ASSOCIATED WITH INDUSTRIAL ELECTRICAL AND VENTILATION EQUIPMENT SUCH AS
FANS AND AIR HANDLING UNITS SHOULD INSTALL THE PRODUCT.
WARNING:
USE LIFTING EQUIPMENT WHICH HAS A SUITABLE SAFE WORKING LOAD FOR THE
EQUIPMENT BEING LIFTED.
WARNING:
ENSURE STEPS, PODIUM STEPS, SCISSOR LIFT OR MOBILE SCAFFOLD TOWER ARE
SECURE AND STABLE BEFORE USE.
WARNING:
MAKE SURE THE CANOPY IS FULLY SECURED BEFORE REMOVING THE SUPPORT
STANDS
Caution:
Supplied packaging provides protection against scratches and scrapes only
2.1.4
Receipt
Step 1:
Check the package is complete to the delivery note and that there are no missing
items.
Step 2:
Check the package is undamaged.
Step 3:
Where items will not be unpacked straight away, check:
Step a)
The shrink-wrap is complete and plastic banding is secure.
Step b)
There are no edges protruding which can become damaged or cause injury.
Where edges are exposed, cover using suitable protection.
Issue: Final
Page 17 of 70
Summary of Contents for Refresh Maxi
Page 71: ......