![Bretford MSB-F2 Assembly Instructions Download Page 2](http://html1.mh-extra.com/html/bretford/msb-f2/msb-f2_assembly-instructions_2808479002.webp)
Substation
Substation
parts removed
for clarity
Floor
monument
Infeed
Infeed
open end
Junction Box
Substation
skin open
position
The open end of the Infeed is to be installed by a certified electrician.
Will require cover plate to have 1 1/8” knock out and an appleton 7289v
connector to complete connection.
STEP 1
Plug the other end of the Infeed into the Junction Box. Close the
Substation Skins.
Fig. 1
Steps to connect Floor Infeed to Junction Box
Note 2. :
Substation Channel instruction sheet step 1 thru step 3 must be completed before
wiring can be done.
Note 1. :