Installation Instructions
Supplies required for installation
• Three (3/8") wall anchors and three (3/8")
bolts
• Minimum 1/2" water supply pipe to connect
to 1/2" NPT connector on hand-held unit
• Pipe sealant or pipe dope
• Sign-mounting hardware
• Vacuum breaker as required by UPC, IPC
and/or local plumbing codes
Step 1: Install mounting bracket to
wall
NOTE: Make sure that, when mounted, the eye
wash unit will measure 33-45 inches from the
top of the sprayheads to the finished floor. For
usage as an eye/face wash, the top of the
sprayheads of the S19-630 must be 33–45
inches from where the user stands per
ANSI Z358.1. The unit must also be
placed a minimum of 6" away from
the nearest wall or obstruction.
1. Install three suitable wall anchors
for use with 3/8" bolts (supplied
by installer) into the wall at the
desired location (see Figure 1a
for eye wash dimensions and
Figure 1b for bracket
dimensions).
2. Bolt the mounting bracket to the
wall using three 3/8" bolts
(supplied by installer).
Step 2: Assemble eye/face
body wash unit
1. Assemble the component parts as
shown in Figure 2 on page 4.
• Be sure to apply pipe sealant to
all pipe joints.
Step 3: Connect water supply
1. Connect the water supply to the
unit (piping supplied by
installer).
2. Mount the safety sign to the wall using the sign-mounting hardware supplied by installer.
3. Open the water supply line. Test for leaks and adequate water flow.
3
Installation
S19-620
Bradley Corporation • 215-866 Rev. S; EN 06-515
6/28/06
10-3/4"
(273mm)
11-1/4"
(285mm)
13-7/8"
(352mm)
33-45"
(838-1143mm)
TO FINISHED
FLOOR
Figure 1a
2"
(51mm)
2"
(51mm)
4"
(102mm)
2"
(51mm)
4-11/32"
(110mm)
27/32"
(21mm)
Figure 1b