Troubleshooting

Problem

Cause

Solution

The signal light and horn (if 

applicable) does not operate 

when water flows .

No power to the signal station .

Check that the circuit breaker or fuse is supplying power to the 

signal station

Component failure .

Check the two 3 Amp 24VDC fuses on the print circuit board in 

the signal station enclosure .

No input power .

Check that there is 24VDC being supplied from the power supply 

mounted on the print circuit board in the signal station enclosure .

Water flowing in wrong 

direction for flow switch body .

Verify that the direction of the water flow corresponds to the arrow 

on the flow switch body .

Insufficient water flow .

Check that water flow is sufficient (2 .4 gallons per minute is 

required) .

Installation error .

Check all electrical connections, including power supply at the 

quick-connect cable, from the signal station to the flow switch .

Horn sounds and signal light 

does not light .

Component failure .

Check light connections and filament in the light .

Beacon light does not 

operate . (This light should 

turn off when the signal light 

turns on and back on when 

the signal light turns off .)

Fixture in use .

Make sure that the flow switch contacts are open (horn and/or 

signal light are not ON) .

Power disconnected in error .

Check that the circuit breaker or fuse is supplying power to the 

signal station .

Component failure .

Check the 3 Amp 24VDC fuses on the print circuit board in the 

signal station enclosure .

No input power .

Check that there is 24VDC being supplied from the power supply 

mounted on the print circuit board in the signal station enclosure .

Component failure .

Check light connections and filament in the light .

Summary of Contents for S19-322

Page 1: ...19 322 Recessed Emergency Signaling System Table of Contents Pre Installation Information 2 3 Components 4 Install Flow Switch 5 Mount Signaling Assembly 6 Connect Signaling Assembly 6 Complete Electr...

Page 2: ...ginning installation and after installation is complete Test the unit for leaks and adequate water flow Main water supply should be ON at all times unless system is being serviced Provisions shall be...

Page 3: ...ire a minimum of 30 PSI 0 21MPa flowing pressure Weekly activation must be conducted on all plumbed emergency equipment to ensure a suitable flushing fluid supply is present and any sediment build up...

Page 4: ...d black and white wires 7 178mm 1 13 16 46mm 13 13 16 351mm NPT Hub Plugged Brass Sensor Body Brass Adapter and Tee 1 2 eyewash or 1 drench shower NPT Inlet and Outlet NEMA 3R Junction Box and Cover E...

Page 5: ...must be in the vertical position with the water pipe horizontal The water flow must be in the direction marked by the arrow on the flow switch body Use teflon tape or pipe sealant supplied by installe...

Page 6: ...customer provided 3 Connect Signaling Assembly to Flow Switch Make sure cable is not taut to prevent undue stress to cable and connector A Connect the flow switch to the signaling system by plugging...

Page 7: ...be empty of water The flow switch is designed to withstand such a water hammer but using the smaller eyewash flow is recommended A Apply power to the alarm branch circuit The alarm should remain in t...

Page 8: ...ng properly once the power is restored by activating the fixture attached to the signaling station Signaling System Maintenance The Bradley Emergency Signaling System is designed to be virtually maint...

Page 9: ...nt 2 4 gallons per minute is required Installation error Check all electrical connections including power supply at the quick connect cable from the signal station to the flow switch Horn sounds and s...

Page 10: ...4 4X 200 6 269 524 1 Cond Cable 6 79 269 2477 1 Ring Lug 1 4 22 16 AWG 80 269 1421 1 Flow Switch 1 1 4 T DPDT 80 269 1522 1 Flow Switch 1 2 T DPDT Item Part No Qty Description 81 269 1902 1 J Box 1 G...

Page 11: ...JUMPER RED 90 264VAC INPUT FLOATING TERMINAL BLOCK WHT WHT BLK BLK GRN GRN FLEX CABLE CONNECTOR BLK BLU RED UNUSED BLU AUX RED AUX BLK AUX FLOW SWITCH DPDT GROUND WIRE CUT 3 AND ATTACHED TO FLOW SWIT...

Page 12: ...ELAY COIL NORMALLY OPEN NORMALLY CLOSED LIGHT HORN FLOW SWITCH FLOW SENSOR COMPONENT SOLDERED WIRE LEGEND CONTACT CONTACT INTERNAL JUMPER TERMINAL BLOCK CONNECTION UNSWITCHED 24 VDC OUTPUT S83 346 S83...

Reviews: