Bradley S19-210SS Installation Download Page 3

Installation

NOTE:  Flush the water supply line before
beginning installation.

Supplies Required:

• (3) 3/8" floor anchors and bolts
• Pipe sealant
• Piping to 1/2" IPS water supply inlet on unit
• Piping to 1-1/4" IPS drain outlet for eyewash
•  Sign-mounting hardware

Step 1: Secure base to floor

1. Install three suitable anchors (supplied by

installer) for 3/8" bolts in the floor (see
Figure 1). 

2. Bolt the base to the floor anchors using 3/8"

bolts (supplied by installer).

Step 2: Assemble eyewash

1. Assemble eyewash components as shown in

Figure 2 on page 4. 

• Apply pipe sealant (supplied by installer)

to all male-threaded pipe joints.

• Use the rubber grip pad provided or a strap

wrench around pipes when tightening to
prevent marring. Place the grip pad on the
pipe, then put the wrench over the grip pad
and turn the pipe with the wrench.

• When connecting the chain, first connect

the chain to the foot treadle “S” hook on
the valve handle. Make sure the chain is
pulled tight (the length of chain used will vary). 

Step 3: Connect water supply

1. Connect the water supply piping (supplied by installer) to the 1/2" IPS inlet on the eyewash. 

2. Connect the drain piping (supplied by installer) to the 1-1/4" IPS drain outlet on the eyewash.

3. Mount the safety sign to the wall using sign-mounting hardware (supplied by installer).

4. Open the water supply lines. Test for leaks and adequate water flow.

3

Installation

S19-210SS

Bradley Corporation • 215-604 Rev. U; EN 06-532G

6/21/07

15-3/8"

(391mm)

35"

(890mm)

40-3/4"

(1035mm)

5-1/8"

(130mm)

6"

(152mm)

Figure 1

NOTE:

All dimensions assume standard thread
engagement. Variations in manufacturing allow
for +/- 1/8" (3mm) per threaded joint. To find
the tolerance of a dimension, add the number
of thread joints in between a dimension and
multiply it by 1/8" (3mm).

Reviews: