Commissioning
7
49
Bosch Security Systems
Seismic Detectors Application Guide
I-200153-1
04.2016
Figure 7-1: Staged commissioning - shock
In Figure 7-1: Staged commissioning - shock the shock test will illuminate the LED as confirmation of
the alarm and the voltage will increase to circa 2.7v DC level as confirmation.
Do not strike the detector as this may cause irreparable damage to the detector.
Figure 7-2: Staged commissioning - integration
In Figure 7-2: Staged commissioning - integration the integration test will illuminate the LED as confir-
mation of the alarm and the voltage will increase to circa 2.7v DC level as confirmation.
The recommended method of recording and verifying the tests is to use the GMXD7 SensTool. See
Section 8 SensTool for additional information.