background image

5

AQ4 Manual

2  AQ4 Installation instructions

2.1 Introduction

Please follow these instructions.  Failure to follow 

instructions may result in:

·  Damage, injury or death

·  Improper operation

·  Loss of warranty

If you are unable to perform the tasks required to 

install the water heater and this accessory properly, 

please  contact  a  locally  licensed  plumber,  HVAC 

contractor or gas technician.

Please  contact  Bosch  Water  Heating  with  any 

questions.

2.2 Locating power vent hood and 

clearances

The maximum vent length from the water heater to 

the point of termination is 25 feet with one elbow. If 

using more than one  90° elbow, subtract 5 feet off 

the maximum vent length for each additional elbow 

used.  Maximum of three elbows allowed.

The power vent motor must be installed 

as close as possible to the VH1-4 vent 

hood.

Clearances
The  vent  system  must  terminate  so  that  proper 

clearances  from  the  center  of  the  vent  hood  (Fig. 

1) are maintained as cited in the National Fuel Gas 

Code, ANSI Z223.1 and CSA B149.1 in Canada:

“The vent terminal shall also not be installed closer than 3 
feet from the inside corner of an L-shaped structure, or less 
than 1 foot above grade or anticipated snow pack level.”

Also: 

“The exit terminals of mechanical vent system shall be located 
not less than 7 feet above grade when located adjacent to a 
public walkway. The venting system shall terminate at least 
3 feet above any forced air inlet within 10 feet. The venting 
system shall terminate at least 4 feet below, 4 feet horizontally 
from or 1 foot above any door, window or gravity air inlet into 
any building.” 

2.3 Power vent hood

1.  Attach  the  mounting  template  (on  page  14) 

to  the  interior  wall  that  the  vent  hood  will  be 

penetrating.

2.  Ensure  that  the  proposed  vent  termination 

clearances are met (Chapter 2.2) before cutting 

opening through wall. Using a 1/2” drill bit, drill 

two pilot holes where noted on the template. The 

drill bit must be long enough to penetrate to the 

building exterior.

3.  Attach the template to the outside of the building 

aligning the pilot holes on the template with the 

pilot holes drilled in step 2. 

4.  Using a reciprocating saw, cut a hole through the 

building  siding,  wall  board,  etc.,  following  the 

appropriate lines of the template. 

5.  Apply a bead of exterior-rated caulk to the vent 

hood flange to seal at the exterior of building.

6.  Slide  the  vent  hood  through  the  opening  and 

fasten to exterior wall using screws provided.

7.  Inspect back draft flapper on hood. If the flapper 

does not properly close, there is a risk of freezing 

air coming into the water heater causing the pipes 

inside to freeze and burst. This condition is not 

covered by the water heater warranty. See Fig. 

11A for a properly closed back draft flapper.

AQ4 Installation instructions

Fig. 1 External vent hood clearances

Summary of Contents for AQ4

Page 1: ...iance Improper installation adjustment alteration service or maintenance can cause injury or property damage Refer to this manual For assistance or additional information consult a qualified installer service agency or the gas supplier In the Commonwealth of Massachusetts this product must be installed by a licensed plumber or gas fitter Upon completion of the installation these instructions shoul...

Page 2: ...Vent piping 7 2 6 Linear safety spillage switch 7 2 7 Flow switch 8 3 Operation 9 3 1 First time start up 9 4 Maintenance 10 5 Troubleshooting 10 5 1 Introduction 10 5 2 Power vent motor runs all the time or intermittently without water flow 10 5 3 Pilot will not hold when lit or spark automatically with hot water flow 11 5 4 Sparks but pilot will not light 5 5 Pilot goes out during hot water use ...

Page 3: ...The power vent motor shaft must be mounted horizontally to prevent motor bearing wear 4 Disconnect power supply when making wiring connections or when working around the fan blade and motor Failure to do so may result in severe personal injury and equipment damage 5 Make certain the power source is adequate for the fan motor requirements Do not add the power vent to a circuit where the total load ...

Page 4: ...g at a minimum height of eight 8 feet above grade directly in line with the exhaust vent terminal for the horizontally vented gas fueled heating appliance or equipment The sign shall read in print size no less than one half 1 2 inch in size GAS VENT DIRECTLY BELOW KEEP CLEAR OF ALL OBSTRUCTIONS 4 INSPECTION The state or local gas inspector of the side wall horizontally vented gas fueled equipment ...

Page 5: ...en located adjacent to a public walkway The venting system shall terminate at least 3 feet above any forced air inlet within 10 feet The venting system shall terminate at least 4 feet below 4 feet horizontally from or 1 foot above any door window or gravity air inlet into any building 2 3 Power vent hood 1 Attach the mounting template on page 14 to the interior wall that the vent hood will be pene...

Page 6: ...r sleeve of the vent hood Fig 4 Use the four pre punched holes in the outlet collar of the power vent motor as a guide to drill diameter holes into the vent pipe Fasten power vent motor outlet to the vent hood inlet using sheet metal screws Seal the connection with high temperature silicone sealant Note Any additional vent pipe used between the power vent motor and the vent hood will be under posi...

Page 7: ... the draft spillage sensing switch will open the pilot safety circuit and shut off all gas to the water heater The switch is normally closed and opens at temperatures greater than 185º F It has a manual reset button Mounting the linear safety spillage switch 1 Attach the spillage switch to the top left of the heater s draft diverter using the existing hole and the included mounting screw Fig 6 2 L...

Page 8: ...lled install before proceeding Open hot water tap to relieve water pressure if water is already connected 2 Remove and save clip on lower right side of hydrogenerator 3 Remove and save pin from front right side of water valve using a flat head screwdriver Fig 8 4 Remove copper pipe and set aside 5 Find and connect the black flow switch to the pipes shown in Fig 9B Note There are two pipes included...

Page 9: ...structions in water heater installation manual 3 1 3 Draft test 1 Operate the water heater by running hot water Check for proper combustion and ensure there is no spillage by holding an recently extinguished match or other visible smoke source in front of the draft divertor The smoke from the extinguished match should be quickly sucked into the opening and up the exhaust venting If the smoke is bl...

Page 10: ... 1 The power vent motor is flow switch activated If the internal paddle inside the flow switch is jammed it may constantly send a signal to turn on the fan Shut off water supply to heater and drain Remove flow switch from water heater piping by removing clips on both ends Flush water through both ends of flow switch to free up internal paddle and clear debris After flushing shake flow switch up an...

Page 11: ...ut during hot water use 1 Inspect entire vent system for blockage or obstruction Ensure the back draft flapper installed on the power vent hood swings freely 2 Verify power vent fan operates with water flow If not verify wire connection from flow switch to fan motor Clean cold water inlet filter and verify flow rate through the water heater is adequate enough to activate the flow switch If flow ra...

Page 12: ...ranty does not cover any labor costs associated with service removal or re installation of part s All such costs must be borne by the Purchaser Additionally this warranty does not cover any labor costs associated with service removal or re installation of the original vent kit or a replaced vent kit How to Make a Claim Any claim for warranty parts should be made to your local dealer distributor or...

Page 13: ...VDC RED 115VAC BLACK BLACK BLACK BLACK WHITE WHITE WHITE GREEN GREEN 115 1 60 PLUG TIMER RELAY POWER VENT MOTOR YELLOW WIRE NUT WIRE NUT C NO NC YELLOW RED TIMER RELAY 2 1 BLUE Wiring Diagram 7 Wiring diagram Fig 12 Fan wiring diagram Fig 13 Safety circuit wiring diagram 425HN and 1600H wiring 425PN and 1600P wiring ...

Page 14: ...l the vent hood will be penetrating 2 Verify that wall penetration will not come in contact with concealed wiring or plumbing Using a 1 2 drill bit drill two pilot holes where noted on the template The drill bit must be long enough to penetrate to the building exterior 3 Attach the template to the building exterior aligning the pilot holes on the template with the pilot holes drilled in step 2 4 U...

Page 15: ...15 AQ4 Manual Notes ...

Page 16: ...BTC 718003301 C Bosch Thermotechnology Corp 50 Wentworth Avenue Londonderry NH 03053 Tel 1 866 642 3198 Fax 1 603 584 1681 www bosch climate us ...

Reviews: