3-1. GENERAL.
Planned maintenance consists of periodic visual and
operational checks, parts inspection, lubrication, and
scheduled maintenance designed to prevent or dis-
cover malfunctions and defective parts. The operator
performs the checks in
, and refers any
required servicing to a qualified maintenance techni-
cian who performs the scheduled maintenance and
any required servicing.
3-2. MONTHLY AND QUARTERLY CHECKS.
is a monthly and quarterly inspection and
service chart based on normal usage of equipment
eight hours per day, five days per week. If the lift truck
is used in excess of forty hours per week, the fre-
quency of inspection and service should be increased
accordingly. These procedures must be performed by
a qualified service technician or your Big Joe service
representative.
3-3. BATTERY CARE.
These batteries are maintenance-free. Any attempt to
open the battery will void the warranty.
Ultra-deep discharging of brand new batteries
should be avoided for at least 15 cycles. To dramat-
ically extend battery life, ultra-deep discharge should
be avoided. The shallower the average discharge, the
longer the battery life.
Charge the battery as described in paragraph
3-4. CHARGING BATTERIES
Charging requirements will vary depending on depth of
discharge and temperature. Follow safety rules when
placing a battery on charge.
Proceed as follows:
1.
Park truck at charging station with carriage low-
ered and key switch and disconnect switch off.
2.
Check the condition of the AC cord, the battery
connector and battery cables. If there are any cuts
in the cable, any exposed wires, loose plugs or
connectors, DO NOT attempt to charge the bat-
teries. Contact appropriate personnel for repairs
to be made.
3.
Connect the charger to connector (13,
). Switch (8) will automatically disconnect the
batteries to from the truck. Make sure connectors
are mated properly.
4.
Connect the charger AC cord to the appropriate
power supply and follow the instructions supplied
with the charger.
Table 3-1 Monthly and Quarterly Inspection and Service Chart
VISUAL CHECKS
INTERVAL
INSPECTION OR SERVICE
Monthly
Check electrical brake for proper operation.
Monthly
Check load wheels for wear. A poly load wheel must be replace if worn to within 1/16 inch of
hub. Check for separation from hub.
Monthly
Check drive wheel for wear. A poly drive wheel must be replace if worn to within 1 inch of
hub. Check for separation from hub.
Monthly
Check entry wheels for wear or damage.
Monthly
Inspect wiring for loose connections and damaged insulation.
Monthly
Check deadman brake switch for proper operation.
Quarterly
Check lift cylinder for leakage.
Quarterly
Check for excessive jerking of steering arm when stopping or starting.
Summary of Contents for PTE 30 Series
Page 12: ...2 6 901467 NOTES...
Page 16: ...3 4 901467 NOTES...
Page 27: ...901467 4 11 NOTES...
Page 28: ...4 12 901467 Figure 4 5 Wiring Diagram Sheet 1 R6490A...
Page 29: ...901467 4 13 Figure 4 5 Wiring Diagram Sheet 1 R6490B...
Page 30: ...4 14 901467 NOTES...
Page 33: ...901467 5 3 Figure 5 2 Control Head and Steering Arm R6507...
Page 36: ...5 6 901467 Figure 5 4 Steering Control R6506...
Page 38: ...6 2 901467 NOTES...
Page 40: ...7 2 901467 Figure 7 1 Drive Assembly R6510...
Page 41: ...901467 7 3 Figure 7 2 Fork Section R6519...
Page 47: ...901467 8 3 Figure 8 2 Frame R6516A...
Page 48: ...8 4 901467 NOTES...
Page 50: ...9 2 901467 Figure 9 2 Hydraulic System R6512...
Page 54: ...9 6 901467 NOTES...
Page 57: ...901467 10 3 Figure 10 2 Steering Control R6506...
Page 59: ...901467 10 5 Figure 10 4 Frame R6516A...
Page 64: ...11 2 901467 NOTES...
Page 66: ...12 2 901467 Figure 12 1 Steering Control R6506...
Page 68: ...12 4 901467 Figure 12 2 Steering Arm R6507...
Page 74: ...12 10 901467 Figure 12 7 Compartment R6521...
Page 77: ...901467 12 13 NOTES...
Page 78: ...12 14 901467 Figure 12 9 Frame R6516A...
Page 80: ...12 16 901467 Figure 12 10 Fork Section R6519...
Page 82: ...12 18 901467 Figure 12 11 Caster Assembly R6518...
Page 86: ...12 22 901467 Figure 12 14 Hydraulic System R6512...
Page 88: ...12 24 901467 Figure 12 15 Pump Motor Reservoir Assembly R6467...
Page 90: ...12 26 901467 Figure 12 16 Cylinder Assembly R6467...
Page 92: ...12 28 901467 Figure 12 17 Valve Assembly R6513...
Page 94: ...12 30 901467 NOTES...
Page 95: ......
Page 96: ...Big Joe Manufacturing Company...