Installation
Section 2: Installation
2.7
Commissioning
!
WARNING
Check that values of electrical supply to the control group (if foreseen) are compatible
with those on the plate on the junction box (Figure 15).
Installation, commissioning and
maintenance and repair works should be made by qualified staff.
Upon actuator commissioning please carry out the following checks:
•
Check that paint is not be damaged during transport, if necessary repair the
damages to paint coat.
•
Check that the pressure and quality of the gas supply (filtering degree, dehydration)
are as prescribed. Check that the feed voltage values of the electric components
(solenoid valve coils, micro-switches, pressure switches, etc.) are compatible
with those reported on the identification plate of the actuator (Figure 1).
•
Check that the setting of the components of the actuator control unit
(pressure regulator, pressure switches, flow control valves, etc.) meet the
plant requirements.
•
Carry out all kinds of operations and check their proper execution (Section 3.3).
•
Check the absence of leakages in the pneumatic connections. If necessary tighten
the nuts of the pipe-fittings.
•
Check proper operation of all the due signalling (valve position, gas supply
pressure etc.).
•
Make a complete functional test in order to verify all the operations are executed
according to operating schematic diagram supplied.