Step 12 Layout Roof Trusses & Install Soffit Blocks

1.

Starting on back corner measure from the backside of the 2x4 gable frame when marking

the location of the first truss. Continue 24" spacing to other gable. Important: When marking
the opposite wall, place the 'X' mark on the same side of the line so your trusses are parallel
when they are installed.

2.

Install metal hangers to the tie plate with 1-1/2" hanger nails . The opening should line up

with the 'X' mark, the bottom of the opening, flush with the 2x4 tie plate. Detail 'D'.

24"

19"

Measure from

Backside of 2x4

Detail 'D'

2x4 Tie Plate

3.

Set roof trusses. Secure trusses to metal hangers with 1-1/2" hanger nails.

2x4 Block with

Gable Frame

Inside of Building

2x4 Block

4.

Gather (22) twenty two short 2x4

blocks and install one at both ends
of each truss. Secure 2x4 blocks
to the soffit panel using (2) two
1-1/2" long exterior screws.

5.

Gather (4) four more 2x4 blocks.

Install one 2x4 block at each end
of the soffit, flush with the 2x4
gable frame.

Summary of Contents for Weston

Page 1: ...not be copied in whole or in part without consent from Reynolds Building Systems Inc Copyright 2018 Building Size 12 x24 Revised November 4 2021 Assembly Book Manufactured by Reynolds Building Systems...

Page 2: ...d optionally You may choose to build your own or pour a cement pad Terminology Square Confirm corners are at 90 degrees Plumb Confirm walls and trusses are straight vertically Wall Plate Top and botto...

Page 3: ...der 4x4 12 Treated Runner Foundation size is 12 0 x 24 0 Check local building codes in your area the construction may have to change For a concrete slab install sill sealer as a moisture barrier betwe...

Page 4: ...t 2 two 2x4 12 to a length of 140 1 2 Position the boards together and indicate with X marks where the wall studs will be located Stud Spacing Top Wall Plate Treated Bottom Plate Do not discard any ma...

Page 5: ...asure the opposite corners These measurements will be the same if the wall is square 4 Install the first OSB panel flush with the side of the wall stud and flush with the top 2x4 plate Nail siding wit...

Page 6: ...supports Nail to the wall stud with 10d sinkers 5 From a pre cut stud cut 5 five blocks to fit between top plate and header Nail through top plate and toenail to header using 10d sinkers 2x4 Block 2x8...

Page 7: ...B to back wall and all 2x4s using 6d common nails spaced 8 apart 3 Install 5 five more OSB panels The last 24 wide panel will extend 3 1 2 past wall to receive front wall panel 4 Start at back wall an...

Page 8: ...ngle cut at one end Nail through the bottom plate with 10d sinkers and secure the top with barbed metal drive on plates Step 6 Assemble Roof Gables 23 1 2 Gable Stud Bottom Gable Plate Barbed Metal Pl...

Page 9: ...rafter and collar tie in place See Detail B 2 Secure the 2x4 truss rafters at the top with a 8 x 20 wood gusset Apply wood glue between the 2x4s and the gusset Nail the gusset to the 2x4s with 14 four...

Page 10: ...over the front and back wall Cut the last filler to fit between the soffit on the sidewalls Front Wall Door Opening 7 Soffit 3 1 2 Filler Step 9 Install Roof Gables Tongue Edge Flush 1 Install a 7 wi...

Page 11: ...o fit against gable on front wall Use 10d sinkers spaced 16 apart 2x4 12 2 Repeat to install tie plates on the opposite side wall Step 10 Install Siding on Gables 1 Locate pre cut gable OSB Install OS...

Page 12: ...th 1 1 2 hanger nails The opening should line up with the X mark the bottom of the opening flush with the 2x4 tie plate Detail D 24 19 Measure from Backside of 2x4 Detail D 2x4 Tie Plate 3 Set roof tr...

Page 13: ...ach board against the keystone and flush with the top of the gable frame Use 6d galv nails spaced 12 apart Side Wall Back Wall The front able trim will be installed in a later step Keystone 82 1 2 Lon...

Page 14: ...x4 Fascia 2x4 Truss Roof Sheathing 2x4 Tie Plate 2x4 Soffit Block Detail E 1x4 6 Fascia Board Straight Edge Nail Fascia to 2x4 Block 6 1 4 1 Install 4 four 42 3 8 long 2x3 boards on the front gable fl...

Page 15: ...d 3 4 past the 2x3s to allow for trim Front Gable Step 16 Install Front Soffit Nail with 6d Common 7 Wide Soffit Panels 42 3 8 Long 2x3 Sheathing Projects 3 4 Upper Roof Sheathing 42 3 8 Long 2x3 3 Re...

Page 16: ...OSB Extends 3 4 Below Trim Step 17 Finish Side Wall Trim Keystone Trim 3 Install a keystone trim board 3 4 above the center of the door opening Use 6d galv nails The exposed siding will serve as a do...

Page 17: ...8 Primed Door Jamb 6 ea 6 Door Hinges 1 ea Door Handle w key 1 ea 6 Barrel Bolt 75 ea 2 Hinge Screws 16 ea White Window Screws Step 20 Install Door Stop on Left Door D o o r S t o p Install a 4 1 4 x...

Page 18: ...nges to the trim temporarily prop the doors in the opening Leave a space at the top and and between the doors and the side trim to allow room for the doors to expand due to humidity 3 Determine positi...

Page 19: ...side Corner Install the siding according to the manufacturer s instructions 1x4 Door Trim J Channel Material List for Vinyl Siding 5 1 2 sq Vinyl Siding double 4 standard profile 4 ea Outside Corners...

Page 20: ...e Siding 48 x 28 angle cut 12 ea Soffit Panels 48 x 7 6 ea Soffit Fillers 48 x 3 1 2 Qty Material Shipped in 4 Extension Kit 2 2x4 for Collar Ties 82 4 2x4 for Truss Rafters 80 1 2 2 1x4 for Side Wall...

Reviews: