8. Handing over of the installation
!
Review and service should be performed by authorised
personnel only.
•
Make repeated start attempts to ensure that the adjustments
function.
•
Close the ball valve during operation to check that the gas switch
switches off at the set value.
•
Remove the hose for the air pressure switch to check that the burner
locks out.
•
Check that all protective covers and measurement nipples are
mounted and fastened.
•
Fill out necessary test reports.
•
Instruct the persons in charge of the operation on the service and
maintenance of the installation and what to do should any troubles
occur.
•
Inspection and service must be carried out by authorized personnel.