5
Bentone
• The electrical installation must be professionally carried out in
accordance with applicable high voltage regulations, as per Enertech’s
recommendations.
• Before servicing, shut off the fuel supply and turn off the power to the
burner.
• Leak checks must be performed during installation and servicing to
prevent fuel leakage.
• Care should be taken by the installer to ensure that no electrical cables
or fuel lines are crushed or otherwise damaged during installation or
servicing.
• If the boiler is equipped with an access hatch, this must be equipped
with a hatch opening switch connected to the burner's safety system.
• When in operation, the burner’s noise level can exceed 85 dBA.
Use hearing protection.
• The burner must not be put into operation without proper safety and
protection devices.
• A Class BE fire extinguisher is recommended.
• It is forbidden to alter thedesign or use accessories which have not
been approved by Enertech in writing.
• Prior to operation, the following points must be checked:
-
fitting and installation work has been completed and approved
-
electrical installation has been correctly performed
-
flue gas ducts and combustion air ducts are not blocked
-
all actuators and control and safety devices are in working order and
correctly set
• After commissioning, if a steady red light on the burner control is
displayed, contact your installation technician.