CONCRETE PAD INSTALL
FIGURE A -
Before installing brick oven, please review local building code requirements in your
area. Brick ovens typically have a minimum setback from all buildings. It may also necessary to
construct a concrete pad to set the unit on. Before construction of the concrete pad it is necessary
to establish Finish Grade height first to ensure the first course of the unit is buried 4”. Once finished
height has been determined construction of the concrete pad can be completed.
FIGURE B -
Sample framework for concrete pad.
FIGURE C -
Sample side view of completed concrete pad.
FIGURE B & C -
A properly constructed level footing is required to place your bottom unit on.
If you are unfamiliar with soil conditions and the process of pouring a concrete footing, please
consult a professional masonry contractor. Be sure to follow all local building codes before
beginning construction.
4” CONCRETE
PAD
6” GRAVEL
BASE
8" CONCRETE
PYLON
NATIVE SOIL
FROST LINE
WOOD FRAME
8" CONCRETE
PYLON
6" GRAVEL
BASE
WIRE MESH
- 8 -
CARDBOARD
FORM