4.4

Connect battery pack

 CAUTION

Risk of electric shock

Dangerous touch voltages can lead to electric shock. To avoid electric shock, observe the following:

• Never plug or unplug the battery pack cable during a thunderstorm.

• Provide protective earthing for handling the battery pack.

NOTE

Incorrect connection procedure

Incorrect procedure when connecting the cable can cause hardware damage.

• Follow the documented procedure for connecting the cable.

• Always connect the cable first and only then switch on the power supply of the connected PC.

After you have mounted the battery pack in the control cabinet, you can connect it to the PC.

Grounding

Potential differences are minimized and electrical currents are diverted to the ground through protective
earthing or potential equalization of electronic devices. This is to prevent dangerous touch voltages and
electromagnetic interference.

Connecting the battery pack

You must connect the battery pack to the PC. For this purpose, there is a 5-pin 2-wire terminal strip with
mounting flange on the battery pack housing (see Fig. 6).

1

5

Fig. 6: C9900-U330_position terminal strip

Table 3: Pin assignment terminal strip

Pin

Function

1

-

24 V battery pack

2

+

3

4

0 V

Power supply

5

24 V

You can connect two wires on each side of a terminal of the terminal strip. For this purpose, you must use
double wire end sleeves (see Fig. 7).

Fig. 7: C9900-U330_double wire end sleeve

PIN 4 and 5 of the battery pack are available for looping through a 24 V power supply to the PC. Accordingly,
you can connect a three-core sheathed cable with plus and minus of the supply voltage as well as protective
earth to the battery pack and then connect the battery pack to the PC with a five-core sheathed cable.

Summary of Contents for C9900-U330

Page 1: ...Manual EN C9900 U330 Battery pack 2022 4 14 Version 3 0...

Page 2: ......

Page 3: ...ntal safety instructions 7 2 4 Operator s obligation to exercise diligence 7 3 Product overview 8 3 1 Structure 8 3 2 Name plate 9 4 Commissioning 10 4 1 Transport and unpacking 10 4 2 Dimensions 11 4...

Page 4: ...Table of contents C9900 U330 4 Version 3 0...

Page 5: ...s The configurations depicted may deviate from the standard Trademarks Beckhoff TwinCAT TwinCAT BSD TC BSD EtherCAT EtherCAT G EtherCAT G10 EtherCAT P Safety over EtherCAT TwinSAFE XFC XTS and XPlanar...

Page 6: ...ead and follow the safety and warning notices Warning of personal injuries DANGER Disregarding the safety notice will lead to death or serious injuries WARNING Disregarding the safety notice may lead...

Page 7: ...utomation engineering background operate the PC to which the battery pack is connected Use by unauthorized persons can lead to damage to property Extinguish the battery pack with foam halogens in case...

Page 8: ...ng The battery pack has a nominal capacity of 3 4 Ah The internal structure of the battery pack consists of two 12 V batteries in series connection The VRLA AGM technology valve regulated lead acid ab...

Page 9: ...del 2 Nominal capacity 3 Internal resistance 4 Fuse 5 Revision 6 Address of the vendor 7 Coded production date 8 Symbols Note here are the symbols applicable to the battery pack such as CE EAC UKCA Th...

Page 10: ...protected from excessive mechanical stress Appropriate packaging of the battery pack in particular the original packaging can improve the vibration resistance during transport On our original packagi...

Page 11: ...ontents and the order or in case of transport damage please inform Beckhoff Service see Chapter 8 1 Service and support 21 4 2 Dimensions All dimensions are in mm Figure 4 shows the dimensions of the...

Page 12: ...ate ventilation of the control cabinet in accordance with EN 50272 2 You can achieve this through natural ventilation Equip the control cabinet with openings for air circulation Position the openings...

Page 13: ...rotective earthing or potential equalization of electronic devices This is to prevent dangerous touch voltages and electromagnetic interference Connecting the battery pack You must connect the battery...

Page 14: ...ed wiring of the battery pack can be found in the following wiring diagrams suitable for your device 1 2 GND 24 V PTC 24 V 3 4 Ah 30 V 9 A C9900 U330 battery pack 3 4 5 1 2 3 4 5 6 7 8 Battery 24 V Po...

Page 15: ...2 3 4 5 ext switch UPS Output ext Switch NO NO X2 X1 UPS Output X2 X1 24 V DC 0 V Industrial PC power connector Power 24 V DC Battery 24 V 1 5 mm 2 Lmax 10 m PTC 24 V 3 4 Ah 30 V 9 A C9900 U330 batte...

Page 16: ...atus 1 2 3 ext switch ext Switch NO NO X2 X1 X2 X1 24 V DC 0 V Industrial PC power connector Power 24 V DC Battery 24 V 1 5 mm 2 Lmax 10 m PTC 24 V 3 4 Ah 30 V 9 A C9900 U330 battery pack 24 V GND 1 2...

Page 17: ...net If you do not want to continue using the battery pack you will receive information on the correct disposal of the battery pack in the further course of the chapter Disassembly from the DIN rail To...

Page 18: ...ack you should insulate the terminals of the removed batteries For this purpose you can use for example insulating tape You can then dispose of the components as follows Dispose of batteries properly...

Page 19: ...V production years 2007 2021 Cleaning NOTE Unsuitable cleaning agents The use of unsuitable cleaning agents can damage the device Clean the battery pack only as specified It is essential to observe t...

Page 20: ...vibration EN 60068 2 6 10 to 58 Hz 0 035 mm 58 to 500 Hz 0 5 G 5 m s2 Shock resistance shock EN 60068 2 27 5 G 50 m s2 duration 30 ms EMC interference immunity conforms to EN 61000 6 2 Permitted ambie...

Page 21: ...you can find on the name plate Beckhoff Support Support offers you comprehensive technical assistance helping you not only with the application of individual Beckhoff products but also with other wid...

Page 22: ...Appendix C9900 U330 22 Version 3 0 8 2 Approvals The device has the following approvals CE EAC UKCA You will find all other applicable approvals on the name plate of your device...

Page 23: ...imensions 11 Fig 5 C9900 U330_DIN rail installation 12 Fig 6 C9900 U330_position terminal strip 13 Fig 7 C9900 U330_double wire end sleeve 13 Fig 8 C9900 U330_wiring diagram 8 pin 14 Fig 9 C9900 U330_...

Page 24: ...List of tables C9900 U330 24 Version 3 0 List of tables Table 1 Key for C9900 U330 structure 8 Table 2 Key for C9900 U330 name plate 9 Table 3 Pin assignment terminal strip 13...

Page 25: ......

Page 26: ...Beckhoff Automation GmbH Co KG H lshorstweg 20 33415 Verl Germany Phone 49 5246 9630 info beckhoff com www beckhoff com More Information www beckhoff com c9900 u330...

Reviews: