5  Start-up 

Before voltage is applied to the equipment the following checks must be performed: 

  Check that screws are firmly seated in 

  Connecting terminals, protective earth conductor terminals and  

potential equalisation terminals 

  Housing cover 

  Check 

  The torque of the cable lead-in 
  The tightness of the seal provided by the cable lead-in 

  Check whether the equipment is ready for operation 

  The parameterisation for this application must have been performed 
  All interfaces such as inputs and outputs for control purposes must be connected 

and ready for operation 

5.1  Parameterisation 

Equipment parameterisation 

  Define all application-specific parameters. 
  Once the power supply is applied, the equipment is ready for operation immediately. 

6  Maintenance / service 

The equipment can only be guaranteed to operate safely and reliably 
in the long term if regular inspections and servicing are carried out. These include the following: 
 
For cleaning the devices it is necessary to take care that no electrostatic charging will be done (no 
high volume flow, cleaning only with damp cloth,…) 

 

An inspection includes 

 

  Visual inspection 

o

  Mechanical damage 

o

  Non-permitted dust deposits 

o

  Other irregularities or error messages from the equipment 

  Checking of components (wearing parts) whose functionality or purpose changes and af-

fects the operation of the equipment 

  Documentation of what was done by whom, and when 

 

Maintenance includes 

  Functionality checking 

o

  Operating statuses such as alarms etc. 

  Checking calibration values (= calibration) 

o

  Triggering of alarms by known process parameters (test pressure etc.) 

  Correction of calibration values (= calibration) must be carried out in the factory 
  Documentation of what was done by whom, and when 

6.1  Time intervals 

Inspection: 

The condition of the equipment must be checked at regular intervals. The time interval is extreme-
ly dependent on the local situation and the degree of use, and must therefore be adapted to re-
quirements. Extremely short time intervals can be specified such as once per day, every new shift 
etc.

 

  Defined by the operator in accordance with local requirements 

Summary of Contents for 901 EX Series

Page 1: ...k Ferdinand Steinbeis Stra e 4 71144 Steinenbronn Operating instructions Pressure Switch Model 901 EX Rev 10 Page 1 of 18 Ident 0607017 BA 901 R10 2017_englisch_Druckversion doc Operating Instructions...

Page 2: ...Dr Ernst Thielicke Operating instructions Pressure Switch Model 901 EX Rev 10 Page 2 of 18 1 General instructions 3 1 1 Safety instructions 3 1 1 1 General safety instructions 3 1 1 2 Safety instruct...

Page 3: ...ings of the symbols that are used are as follows Useful important additional information Dangers and safety instructions Important please read Failure to comply with these instructions can have a detr...

Page 4: ...d out Dust deposits must be avoided installation location protection cleaning etc in order to prevent dangerous surface temperature increases For the installation procedure it is necessary to take car...

Page 5: ...ve gasses and dust natural gas bio gas solvents etc Liquid Flammable liquids petrol solvent etc Use in zones in potentially explosive areas Pressure switches are used to monitor the pressure differenc...

Page 6: ...with the specified zones With intrinsically safe systems i the associated operating materials barrier must al ways be installed outside the potentially explosive area The labelling of the product must...

Page 7: ...ory corresponds with the specified zones No potentially explosive atmosphere is present A release for work must have been issued by the operator Adherence to the applicable regulations and documentati...

Page 8: ...being connected are not live otherwise there is a risk of igniting a potentially explosive atmosphere Attach the shield Attach shield at one end in non potentially explosive area Attach braiding of sh...

Page 9: ...ions and servicing are carried out These include the following For cleaning the devices it is necessary to take care that no electrostatic charging will be done no high volume flow cleaning only with...

Page 10: ...cturer The following must be observed in potentially explosive areas No potentially explosive atmosphere is present A release for work must have been issued by the operator The applicable regulations...

Page 11: ...r 100 mA 24 VDC for Dust 2D 30V 60mA 0 6W Electrical connection Arrangement of contacts for 901 1 901 30 901 41 901 51 EX only for 901 2 EX for 901 6 901 8 901 9 EX only for 901 7 EX Certifications CE...

Page 12: ...e Tolerance band in of trip pressure Maximum positive working pressure standard extended Maximum negative working pressure standard extended 901 1 EX 5 mbar 200 mbar 2 5 mbar 50 mbar 10 0 5 4 bar 1 ba...

Page 13: ...standard extended Maximum negative working pressure standard extended 901 61 EX 5 20 mbar 10 3 mbar 0 5 4 bar 1 bar 901 62 EX 10 50 mbar 10 5 mbar 0 5 4 bar 1 bar 901 63 EX 25 100 mbar 10 10 mbar 0 5...

Page 14: ...d accessories Beck GmbH Druckkontrolltechnik Ferdinand Steinbeis Stra e 4 71144 Steinenbronn Operating instructions Pressure Switch Model 901 EX Rev 10 Page 14 of 18 9 2 Dimensioned drawings and acces...

Page 15: ...Appendix Beck GmbH Druckkontrolltechnik Ferdinand Steinbeis Stra e 4 71144 Steinenbronn Operating instructions Pressure Switch Model 901 EX Rev 10 Page 15 of 18 9 2 2 Pressure switch 901 Prescal...

Page 16: ...Declaration of Conformity Beck GmbH Druckkontrolltechnik Ferdinand Steinbeis Stra e 4 71144 Steinenbronn Operating instructions Pressure Switch Model 901 EX Rev 10 Page 16 of 18 9 3 Declaration of Co...

Page 17: ...rolltechnik Ferdinand Steinbeis Stra e 4 71144 Steinenbronn Operating instructions Pressure Switch Model 901 EX Rev 10 Page 17 of 18 9 4 EC design test certification Note More documentation for EC des...

Page 18: ...ction class Zone 2 22 Gc Dc Zone 2 22 1 21 Gb Db Zone 1 2 21 22 Ex ia IIB Ex ia IIIB 0 20 Ga Da Zone 0 1 2 20 21 22 Ex ia IIC CHARACTERICTICS Intrinsically safe operating materials Associated operatin...

Reviews: