Wait a minimum of 6 minutes 30 seconds before working on the interior components to allow the capacitor to discharge.
See
"Servicing" for removal of case panel, door etc.
14.1 Supplementary & Engine Igniter (
1. Disconnect the igniter plug and the electrode leads, noting their positions.
2. Undo the screws securing the igniter and remove it being careful to retain the washers.
3. Reassemble in reverse order.
14.2 Supplementary Igniter and Sensing Electrodes (
1. Disconnect the electrode leads, noting their positions.
2. Remove the retaining screws securing each of the electrodes to the burner door and withdraw the electrodes.
3. Replace the sealing gaskets.
4. Reassemble in reverse order.
Fig. 56
Fig. 57 & Fig. 58
14.3 Engine Igniter and Sensing Electrodes (
Summary of Contents for ECOGEN 24/1.0
Page 69: ...Fig 77 Fig 78 Fig 79 page 69 16 0 Schematic Wiring 16 1 Burner Control Units BCU Connections...
Page 70: ...page 70 16 2 Milligrid 24 way Connector...
Page 71: ...page 71 16 3 14 way Connector...
Page 72: ...page 72 16 4 Engine Circuit...
Page 73: ...page 73 16 5 Power Monitoring 24Vdc Power Supply...
Page 74: ...page 74 16 6 External Connections External Wiring...
Page 85: ...page 87...
Page 86: ...page 88...
Page 87: ...page 89 Section P...
Page 88: ...page 90...
Page 89: ...page 91 Section Q Engine developing less than 950W after 15 minutes running at maximum rate...
Page 91: ...page 93 page 94 page 95 page 96 MICRO CHP SYSTEM COMMISSIONING CHECKLIST...
Page 92: ...page 97...