Réf.  :  CI - 389 - C

1.  C

ommissioning

BAXI does not accept any liability for damage caused
by work that does not comply with these instructions
and/or which has not been carried out by a qualified
installer.

1 - 1  Filling

- Water quality for the heating system

Avoid using hard water, which may scale the boiler. If TH
or total hardness is above the French 25°, the boiler
should be filled with softened water.

- Filling the boiler and heating system

While filling, which must be done slowly, ensure that the
stop valves are open and that the mixing valve can be 1/
2 open.
The automatic drain cock plug, normally fitted on the
boiler outlet, must remain untightened in order to achieve
continuous draining during filling-up. Drain all high points
of heating system and close the various draining screws
one after the other as soon as water reaches their level.
After filling the boiler for the first time, flush completely
(using the sludge flushing valve) in order to get rid of
foreign bodies that may come into the components or the
pipes during assembly.

- Water topping up

Subsequent boiler topping-up should be practically non-
existent and in all cases controlled and registered by a
water flow meter. Frequent topping-up is the a symptom
of a leakage which should be repaired as soon as possi-
ble.

1 - 2  Preliminary checks

When commissioning the boiler for the first time in the
season, or after a prolonged shutdown period :

- ensure that filling was done properly and check overall

tightness. If necessary, put more water and drain all high
points until water flows slightly.

- check the connection of the flue stack and the proper

working condition of the draught regulator if any

- check that the high and low vents are not obstructed
- ensure that the doors and the flue access plates are

closed and tight
If necessary, act upon the tightening points.

- ensure that the burner is properly locked
- check if it is properly supplied in fuel, that supply and

return valves are open

- for operation with gaseous fuel types, check that the

safety conditions are fulfilled.

2.  O

peration

2 - 1  Principle

Boiler control is done through the thermostats (10) or through
built-in weather-compensated control (optional).
Operation safety is ensured by the limit thermostat (13) with
manual reset.

For boilers fitted with a W.C. control, the boiler water
temperature is adjusted by action on the burner and (or) on
the mixing valve, depending on outside temperature.

Summary of Contents for CHAPPEE NXR4

Page 1: ...RIZED CAST IRON OIL OR GAS BOILERS U S E R 1 Commissioning 1 Filling 2 Preliminary checks 2 Operation 1 Principle 2 Heatingboileralone STANDARD 3 Heating boiler alone with an ECOCONTROL panel 3 Start up 4 Shutdown 5 Safety recommendations 6 Maintenance 7 Possible servicing needs 8 Recommandations ...

Page 2: ...hould be practically non existent and in all cases controlled and registered by a water flow meter Frequent topping up is the a symptom of a leakage which should be repaired as soon as possi ble 1 2 Preliminary checks When commissioning the boiler for the first time in the season or after a prolonged shutdown period ensure that filling was done properly and check overall tightness If necessary put...

Page 3: ...uired boiler temperature Set the 1st stage thermostat on the left at about 5 to 10íC above this setting about one figure on the index Example 2 nd stage thermostat on 75 C 1 st stage thermostat between 80 and 85 C Lit when thermostat 13 is activated after abnormal increase in boiler water temperature The burner is stopped Factory set at 110 C manual reset Power ON light Swicht Burner ON Off Test f...

Page 4: ...s disconnectthefluestackandclosethefluehoodtoavoidany air circulation inside Thesystemmustnotbedrained exceptiftheboilermaynot be started up at the beginning of the cold season Antifreeze An efficient protection against freezing can be obtained by incorporating a certain amount of antifreeze in the heating system Centralheatingantifreezeisofaspecialgrade Yourinstaller shall give you all useful det...

Page 5: ...ways done with the boiler cycled off and the power supply cut out Proceed as follows put ON burner switch located on the control panel as well as the main heating system switch removecasingfrontpanels open combustion chamber burner support door and removesmokehoodplugs clean the walls of each flueway with the brush provided with the boiler as well as the combustion chamber walls flush soot and com...

Page 6: ...ors Clean the boiler at least twice during the heating season Checktheburnersettingsatleasttwiceduringtheheating season 8 Recommendations Settheboilerthermostataccordingtooutsidetemperature inordertoavoidoverheatingtheradiators Werecommend to install a control system to be integrated in the control panel which acts upon the burner and limits operating time of the latter 4 if the control box is not...

Page 7: ...7 Réf CI 389 C NOTES ...

Page 8: ...8 Réf CI 389 C PRINTED AT SOISSONS FACTORY FRANCE 157 AVENUECHARLESFLOQUET 93158LEBLANCMESNILCEDEX FRANCE TELEPHONE 0145915600 FAX 0145915950 www chappee com ...

Reviews: