Assembly and installation
Ensure the following prior to installation of the flow sensor:
n
The higher-level machine is in a safe state for the installation of
the flow sensor.
5.1 “Prerequisites for installation” on page 31
n
The installation position of the flow sensor has been selected
according to the criteria of the system and the requirements of
the flow sensor.
5.2 “Installation position of the flow sensor” on page 32
5.1 Prerequisites for installation
When installing the flow sensor in the higher-level machine, the fol-
lowing must be observed for the mounting location:
n
The flow sensor must not be exposed to excessive vibration at
the installation site.
n
The flow sensor must not be overly dirty at the installation site.
n
The flow sensor must be protected from direct sunlight at the
installation site.
n
The installation site must allow proper grounding of the flow
sensor.
n
The installation site must allow the proper electrical connection
of the flow sensor.
n
The flow sensor must be freely accessible at the installation
site at all times.
n
Mechanical effects on the flow sensor must be excluded during
operation.
n
During installation, the recommended and avoidable installa-
tion positions of the flow sensor must be observed:
5.2 “Installation position of the flow sensor” on page 32